Salzgitter's first nine months of 2026 look like a turnaround: net profit of €177.2 million against a €46.5 million loss a year earlier, sales up 6.8% to €7.33 billion, and guidance raised twice. But the composition of that recovery matters more than the headline. Strip out accounting and portfolio effects and the picture is less dramatic — and more instructive — than the reported numbers suggest.

What actually moved the earnings

Reported EBITDA rose from €224.0 million to €534.9 million. That comparison flatters the operating story. The adjusted measure the company uses for guidance — EBITDA VX, which excludes valuation effects on the bond exchangeable into Aurubis shares — was €659.1 million. The €124.2 million gap is a non-cash valuation charge on that instrument; no equivalent effect was booked in the prior-year period. So the true operational delta is larger in absolute terms but different in composition.

The more important distortion is Aurubis itself. The copper producer contributed €252.0 million at-equity in the period, versus €83.5 million a year earlier — roughly 38% of EBITDA VX. For a company classified as a steelmaker, that is a striking dependency. Salzgitter has long held this stake, but with copper prices firm and Aurubis earnings strong, the contribution has become first-order. Any analysis that treats Salzgitter as a pure steel proxy will misread both its earnings volatility and its resilience.

Segment data reinforces the point. Technology (KHS filling and packaging systems) delivered EBT of €99.0 million, now the group's largest single contributor ahead of Steel Production at €93.9 million. Trading contributed €53.3 million, and the Industrial Participations/Consolidation line swung to €52.1 million from –€23.3 million, driven largely by the Aurubis effect.

Segment (€m)External sales 9M26EBITDA 9M26EBT 9M26EBT 9M25
Steel Production3,006.3271.293.9–61.2
Steel Processing847.8–33.8–69.0–85.3
Trading2,018.272.753.320.8
Technology1,307.1116.799.076.2
Industrial Participations/Consol.150.4108.252.1–23.3

Source: Salzgitter Group 9M 2026 quarterly statement (EQS-News, 12 November 2026).

The Steel Production segment is where the HKM acquisition shows up. Revenue rose 16.0% and EBITDA swung by €149.9 million, the largest single improvement in the group. Steel Processing remains loss-making, at –€33.8 million EBITDA and –€69.0 million EBT, reflecting the still-weak German automotive and machinery demand that has weighed on downstream flat-product processors for two years. That is the segment most exposed to a genuine demand recovery — and it has not arrived.

Volumes: growth in the wrong product

The headline crude steel figure — 4.90 million tonnes, up 11.3% — is almost entirely a consolidation artefact. HKM's output entered the group perimeter from July 2026 after Salzgitter acquired the remaining 50% from thyssenkrupp Steel and Vallourec. This is not organic growth.

The rolled/crude ratio tells the deeper story. In 9M 2026, 3.40 million tonnes of rolled product against 4.90 million tonnes of crude implies a ratio of roughly 69%. In 9M 2025, back-calculating from the reported growth rates gives about 76%. That six-to-seven percentage point drop reflects HKM's product mix: it is a producer of slabs and round steel (roughly 180–430 mm), largely sold or transferred as semi-finished material rather than rolled in-house. Shipments rose 11.3%, matching crude steel growth exactly, while rolled steel rose only 1.6%. The incremental tonnage is semis.

The practical implication: Salzgitter's crude steel output is now an increasingly poor proxy for its exposure to rolled-product markets. Investors and analysts tracking the company's exposure to European flat-steel pricing need to watch rolled steel volumes and the Steel Processing segment, not the crude headline.

Guidance and the embedded caution

The upgraded full-year outlook — sales around €10.0 billion, EBITDA VX of €800–875 million (from €725–825 million) and EBT VX of €400–475 million — looks confident. But the arithmetic reveals caution. At the €837.5 million midpoint, Q4 EBITDA VX would need to be around €178 million, against a 9M quarterly average of roughly €220 million. Even the top of the range implies Q4 of only about €216 million. Management is explicitly not extrapolating the third quarter's strength.

Given the company's own note that forecasting reliability is limited in the final quarter, and given the persistent weakness in German industrial demand, that conservatism is prudent. It also leaves room for a positive surprise if Q4 holds near the 9M run-rate.

HKM's full consolidation is expected to add a mid-double-digit million-euro amount to both EBITDA VX and EBT VX in 2026, subject to purchase price allocation effects, and a mid-triple-digit million-euro amount to external sales. Those are reported expectations, not my estimates, but they underline how much of the 2026 improvement is portfolio-driven.

Cost programme: the one genuinely operational win

The P28 programme is the clearest evidence of real operational progress. It delivered €146 million in sustainable earnings improvements in the first nine months, against a full-year target of €122 million. Cumulative improvements since the 2024 launch stand at approximately €390 million, including €134 million carried over from the predecessor Performance 2026 programme. The full target is €575 million by 2028.

This is meaningful because it is internally generated, repeatable and not dependent on copper prices or consolidation effects. That P28 has already exceeded its full-year target by a fifth suggests the procurement, logistics and technology levers are working. The remaining gap to the 2028 target — roughly €185 million over two years — is a reasonable ask if execution holds, though it will get harder as the easier savings are captured.

The transformation projects: on track, on cost, and the real test ahead

SALCOS stage one — a direct reduction plant, a 100 MW electrolyser and an electric arc furnace at the Salzgitter site, targeting around 2 million tonnes of low-carbon crude steel — is scheduled to deliver first steel in the second half of 2027. Management reaffirmed that late-summer 2027 target on the earnings call and explicitly said higher electricity prices would not delay it.

Energy cost is the central risk. The average spot electricity price in 9M 2026 was €108/MWh, about 20% higher year on year. Salzgitter has hedged much of its 2026 and part of its 2027 exposure through PPAs and forward contracts, and has a long-term solar-backed supply contract for 147 MW. From March 2028, contracted wind and solar output is expected to provide around 1.7 TWh per year. The hedging covers the ramp-up period; it does not solve the structural cost gap with US or Middle Eastern gas-based DRI producers, but it buys time.

At Duisburg, the parallel transformation is more immediately visible. HKM's Blast Furnace A was permanently decommissioned at the end of Q3 2026 after more than 53 years of operation, with the final tap in September. An electric arc furnace of up to 2.5 million tonnes annual capacity, supplied by Tenova under a contract signed in July 2026, is under construction with completion scheduled for 2029. That is Germany's largest EAF, and it will operate alongside the existing BF B, giving HKM a hybrid route in the interim.

ProjectLocationKey equipmentCapacityTimeline
SALCOS stage 1SalzgitterDR plant + 100 MW electrolyser + EAF~2 Mt low-carbon crude steelFirst steel H2 2027
HKM EAFDuisburgTenova EAF (largest in Germany)Up to 2.5 MtCompletion 2029
HKM BF ADuisburgBlast furnaceDecommissionedEnd Q3 2026

The decommissioning of BF A is significant beyond Salzgitter. It removes one of the older, less efficient blast furnaces from the German market at a time when domestic steel demand remains weak, and it signals that Salzgitter is prepared to retire capacity permanently rather than idle it — a decision that reduces fixed costs but also locks in a lower blast-furnace footprint ahead of the EAF start-up.

What to watch

The 2026 results should be read as a portfolio and cost story, not a demand recovery. The four things that matter for the next twelve months:

  1. Q4 delivery. Whether the company hits the middle or top of guidance will depend on whether Steel Processing stops bleeding and whether Aurubis's contribution holds.
  2. SALCOS ramp-up. First steel in H2 2027 is the proof point for the entire German DRI-EAF model. Any slip would raise questions about the economics of hydrogen-based steelmaking in a high-electricity-price environment.
  3. HKM integration. The 2029 EAF completion will determine whether Duisburg becomes a competitive low-carbon semis supplier or a stranded asset. The purchase price allocation effects in 2026 are a distraction; the operational integration is not.
  4. EU trade policy. Revised trade defence measures and CBAM have improved competitive conditions for European producers, according to the company. That tailwind is real but partial — it protects against imports, not against weak domestic demand.

The headline profit is welcome after a difficult period. But the more useful signal is structural: Salzgitter is becoming a more diversified industrial group in which steel is one earnings stream among several, and the transformation of its steelmaking footprint is proceeding on schedule despite energy costs that remain a competitive disadvantage. That is a harder story to sell than a €177 million swing, but it is the one that will determine the company's position in 2030.

Source & methodology +

MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.

Article status
Published · Version 1
Source date
12 November 2026
MetalMate publication
13 November 2026
Verification
Automated evidence checks; not human reviewed

Germany's Salzgitter posts net profit in Jan-Sept 2026, crude steel output rises 11% — SteelOrbis