Industrial projects, independently researched.

Steel-intensive projects investigated from primary sources by MetalMate’s AI research analyst. Each article is AI-generated and should be independently verified.

113 published projects6 industries8 regions

113 of 113 projects

Showing all published projects
EuropeContract award

LanWin2 Moves Into Steel: TenneT's 2 GW North Sea Link Enters Fabrication as Jacket Award Completes the Supplier Map

With Nexans extruding 525 kV cable at Halden, Siemens Energy/Dragados cutting first steel in Italy and the UAE, and Eiffage Smulders now contracted for the LanWin beta jacket, TenneT's 2 GW LanWin2 connection has moved decisively from award to fabrication — and the remaining steel demand is concentrated in the platform topside and jacket programmes already placed.

Offshore renewables · Updated 2026-11-17
AI-generated image
North AmericaOperational

Nucor Berkeley Starts Up Its Second Galvanizing Line: A $425M Bet on Automotive-Grade Coated Steel Begins Its Ramp-Up

Nucor has produced the first prime coil on its new ~500,000 ton/year continuous galvanizing line at Nucor Steel Berkeley in Huger, South Carolina, supplied by Primetals Technologies with Clecim mechanical packages — starting a ramp-up that Nucor expects to reach full run rate only by the end of 2027.

Industry & mining · Updated 2026-11-08
AI-generated image
EuropeConstruction / fabrication

Marcegaglia's €1.2bn Fos-sur-Mer EAF: Mistral financing is in place — but the FID still isn't

Marcegaglia has locked in €800m of SACE/Bpifrance-backed sustainability-linked debt and a €450m Danieli equipment contract for its Mistral electric-furnace steel complex at Fos-sur-Mer, but final investment decision, permits and the civil-works/construction-steel packages are all still outstanding ahead of a target 2029 start-up.

Industry & mining · Updated 2026-11-07
AI-generated image
EuropeConstruction / fabrication

East Anglia Two moves into the delivery phase: foundations, the Wind Ace and what the steel procurement record actually shows

ScottishPower Renewables' 960 MW East Anglia Two has moved into construction, with Sif and Smulders building 64 monopiles and transition pieces, HSM the offshore substation, and Cadeler's new Wind Ace due to install from 2027; the monopile plate supply chain remains largely undisclosed.

Offshore renewables · Updated 2026-11-04
AI-generated image
EuropeConstruction / fabrication

Keel Laid at Nantong: Wison's Sakarya Phase 3 FPU Enters Hull Assembly, With Steel Work Only Half Done

Wison New Energies has laid the keel for TPAO's 282 m Sakarya Phase 3 FPU in Nantong, moving a 25,000 t topsides and ultra-deepwater hull into assembly — but the schedule stated to Türkiye's state oil company and the timeline reported by trade press differ by roughly a year, and steel supply details remain undisclosed.

Energy · Updated 2026-11-03
AI-generated image
Asia ex-ChinaConstruction / fabrication

GS Entec Turns Ulsan Refinery-Equipment Works into Asia's Largest Monopile Plant — and a 150,000 t/yr Thick-Plate Demand Point

GS Entec has completed a roughly KRW 300 billion conversion of its Yongjam Works in Ulsan into a dedicated, Sif-licensed monopile line, lifting capacity from 40,000 to 150,000 t/yr and moving into the 15 MW+ class — with Taean's 37 monopiles as the first anchor order and Japanese export ambitions next.

Offshore renewables · Updated 2026-11-02
AI-generated image
North America · EuropeAnnounced

A Framework, Not a Contract: What the Swiss Steel–Canada Nickel 1 Mt/y Low-Carbon Billet Plan Actually Commits To

Swiss Steel and Canada Nickel have signed only a framework of intent for up to ~1 Mt/y of low-carbon stainless and specialty billets and blooms from 2030. The real story is the two-year schedule gap between Crawford's 2029 start and Swiss Steel's industrial strategy — and who carries that risk.

Industry & mining · Updated 2026-11-02
AI-generated image
EuropeConstruction / fabrication

East Anglia Three: Foundations In, Turbines Turning — Inside the 1.4 GW Build and Its Spanish Steel Backbone

All 95 monopiles and transition pieces at East Anglia Three are installed and the 240 km inner-array cable campaign is complete, with 95 Siemens Gamesa 14 MW turbines going up ahead of a targeted end-2026 commissioning. A look at the multi-contract delivery model, the now-closed foundation supply chain and what remains.

Offshore renewables · Updated 2026-11-02
AI-generated image
Asia ex-ChinaFeasibility / FEED

POSCO and Hanwha Ocean take high-manganese steel from LNG fuel tanks into cargo containment

A non-binding MOU pairs POSCO's cryogenic high-manganese steel with Hanwha Ocean's membrane LNG carrier experience, targeting a demonstration vessel that could lift steel content per ship from roughly 1,000 tonnes to more than 10,000 — but no class approval, schedule, shipowner or order is yet in the public record.

Marine & shipbuilding · Updated 2026-11-02
AI-generated image
GlobalConstruction / fabrication

voestalpine's Donawitz EAF: How a €420 Million Furnace Became the Test Case for Special-Steel Decarbonisation

voestalpine has finished installing the electric arc furnace at its Donawitz special-steel works in Leoben, Austria, and begun cold commissioning — a €420 million conversion that must eventually make railway, wire and tube grades from scrap-heavy feedstocks, with first operation targeted for H1 2027.

Industry & mining · Updated 2026-11-02
AI-generated image
EuropeAnnounced

RESOLVE: Aker Solutions Wins EU Innovation Fund Selection for Automated HVDC Topside Steel Fabrication Line

Aker Solutions' RESOLVE project has been selected under the EU Innovation Fund's IF25 manufacturing call to build an automated laser-hybrid welding line for offshore wind HVDC topside steel structures, claiming ~10 months of schedule savings — but the grant is unsigned and no site, capex, tonnage or steel specification has been disclosed.

Offshore renewables · Updated 2026-11-02
AI-generated image
Asia ex-ChinaAnnounced

제강슬래그로 고속도로를 포장한다: 철강협회·도로공사·아스콘연합회 3자 협약의 의미와 남은 과제

한국철강협회·한국도로공사·한국아스콘공업협동조합연합회가 2026년 8월 11일 체결한 제강슬래그 활용 친환경 아스팔트 포장 업무협약을, 표준·품질·수요처라는 세 축에서 분석하고 실제 발주로 이어지기 위한 조건을 짚는다.

Infrastructure · Updated 2026-11-02
AI-generated image
North AmericaAnnounced

HPLS: Inside Hyundai and POSCO's $5.8 Billion Louisiana Steel Bet — Equipment Awards, Civil Works and the Automotive Supply Chain It Is Built For

HYUNDAI-POSCO Louisiana Steel is building a $5.8 billion, 2.7 Mtpa electric-arc-furnace flat-products mill at Donaldsonville, Louisiana, targeting 2029 start-up to feed Hyundai and Kia US assembly plants — with Danieli, Tenova and SMS group now locked in as process technology suppliers.

Industry & mining · Updated 2026-11-02