The award itself is unremarkable: Eiffage Smulders, the Belgian offshore steel subsidiary of Eiffage Métal, has taken a jacket-foundation subcontract from Dragados Offshore for the LanWin beta converter platform, part of TenneT's LanWin2 2 GW HVDC connection in the German North Sea. Work starts early 2027, load-out is planned for 2030.
What makes it worth attention is not the contract but the map it draws. A Spanish contractor (Dragados, Algeciras), working with Siemens Energy under a TenneT framework, has subcontracted structural steel to a French-owned Belgian fabricator whose production is split between Belgium and Poland and whose final assembly and load-out happen in the Netherlands — for a German grid connection supplied with Italian and Emirati steel blocks and French cables. That is not incidental complexity. It is the shape of the 2 GW era.
The platform, the jacket and who does what
The LanWin2 offshore converter station converts 66 kV AC from the wind farm array to ±525 kV DC for transmission to an onshore converter in the Heide region of Germany. The topside is Dragados Offshore's scope; the jacket is now Smulders'.
The supply chain around LanWin2, as disclosed by the companies involved:
| Scope | Party | Location | Status |
|---|---|---|---|
| Platform EPCI (with Siemens Energy consortium) | Dragados Offshore | Algeciras, Spain | Contract signed with TenneT April 2023; Algeciras construction works started April 2026 |
| Topside steel blocks | Cimolai | Italy | First steel cut September 2025 |
| Topside steel blocks | Eversendai | Ras Al Khaimah, UAE | First steel cut September 2025 |
| Jacket design | KCI the engineers (Sif Group) | Netherlands | Awarded by Dragados |
| Jacket fabrication | Eiffage Smulders | Belgium + Poland | Awarded November 2026; start early 2027 |
| Jacket final assembly and load-out | Smulders | Vlissingen, Netherlands | Planned 2030 |
| Export cable systems (250 km, 525 kV HVDC XLPE) | Nexans | France/Norway | ~€1 billion EPCI; manufacturing began October 2026 |
Two details in that table carry more weight than the rest. First, the design of the jacket sits with KCI, a Sif Group subsidiary — meaning the structural engineering of the substructure and the fabrication of it are now separated by contract, and the fabricator builds to another party's design. That is a meaningful shift in risk allocation for a structure of this size, and it narrows the fabricator's ability to optimise for its own yard constraints. Second, the fabrication split itself: Smulders' Polish sites at Żary, Łęknica and Niemodlin produce secondary steel for foundations, with components moved by road to other Smulders branches, where the heavy lifting and assembly capacity sits. This is the same model Smulders used for the Centre Manche 1 and 2 jackets in Normandy (each around 7,000 tonnes, fabricated in Belgium, finally assembled at Vlissingen) and for the OSS Jasmund jacket, which reached roughly 4,500 tonnes load-out weight from Vlissingen.
Smulders' own yard data make the logic clear: Vlissingen offers 175,000 m² of site area and 1,200 tonnes of lifting capacity with direct North Sea access, Hoboken offers over 600 tonnes of lifting on the Scheldt, and Poland offers 39,400 m² of production space at lower cost but no water access. Low-cost, labour-intensive fabrication in Poland; precision and heavy assembly in Belgium and the Netherlands; load-out where the water is deep enough.
Why the 2 GW standardisation pushes work across borders
TenneT's 2 GW programme was designed around a standardised platform concept — same topside architecture, same converter configuration, repeated across BalWin3, LanWin2 and LanWin4 in the German sector and equivalent projects in the Dutch sector. Standardisation should, in principle, make fabrication simpler. In practice it has done something else: it has turned offshore converter platforms into a repeatable product with a multi-year order book, which allows contractors to allocate blocks of work across a portfolio of yards rather than reserving one.
That is precisely what the Algeciras/Smulders arrangement shows. Dragados keeps topside integration, outfitting and commissioning testing at Algeciras; the steel blocks come from Cimolai and Eversendai; the jacket goes to Smulders' Belgian-Polish-Dutch chain. Each party is doing what its yards are best at, and the platform's schedule is governed by the slowest link rather than by any single site.
The steel-intensity of this model is underappreciated outside the sector. These are not wind-turbine foundations in the conventional sense — a 2 GW HVDC platform topside plus its jacket is among the largest fabricated steel structures built offshore, comparable in steel mass to a large offshore oil and gas platform. A single 2 GW connection consumes export cable in the hundreds of kilometres (250 km for LanWin2) and platform steel in the thousands of tonnes. TenneT's programme, spanning multiple such connections, is effectively a new demand category for heavy structural fabrication in Europe — one that European yards, not Asian ones, are currently winning, because the platforms must be integrated and tested close to their installation sites.
The schedule signal and its caveats
The dates deserve scrutiny because they are the part of this announcement most likely to change. Smulders and Eiffage state only that work begins in early 2027 and that load-out is foreseen in 2030. Trade reporting attributes a 2031 commissioning date to LanWin2. Nexans' own January 2025 release, when the cable contract was awarded, stated commissioning was expected in 2030.
That is a genuine conflict between a primary corporate source and trade press, and the most defensible reading is that the schedule has slipped by roughly a year between the 2025 cable award and the 2026 jacket award — consistent with the pattern across the European offshore grid build-out. Readers should treat 2031 as the operative expectation and 2030 as the original plan. Notably, the £1 billion figure sometimes misreported for the Nexans cable contract is a transcription error; Nexans' own release puts the LanWin2 cable package at approximately €1 billion.
The load-out date is also the more commercially meaningful one. A 2030 load-out implies jacket fabrication must be substantially complete by late 2029, which in turn implies the Polish secondary-steel work needs to be flowing by mid-2028 to feed Belgian assembly. For a fabricator running several TenneT-platform jackets plus the French Centre Manche work through the same yards, that is a tight sequencing problem, not a slack one.
What to watch
- Whether the Belgian-Polish-Dutch split is replicated. If Smulders runs the same structure for further TenneT 2 GW platforms, it becomes a de facto standard for European jacket supply rather than a one-off optimisation.
- Algeciras throughput. Dragados started construction works at its Algeciras yard in April 2026 and is receiving upper grillage beams for LanWin2. The yard's ability to process multiple 2 GW topsides in parallel is the binding constraint on the whole programme.
- Design-fabrication separation risk. KCI's design ownership means any late engineering change sits with Sif's engineering arm, not with the fabricator. Watch for change-order friction as jacket details meet yard realities.
- Cable and platform schedule alignment. Nexans began manufacturing LanWin2 subsea cable in October 2026, well ahead of jacket steel. If the platform slips further, cable storage and installation windows — not steel — become the programme's critical path.
For steel fabricators and heavy engineering suppliers outside this consortium, the broader point is that Europe's offshore grid is now a durable, standardised, multi-decade order book for large structural steelwork — and the winners are the yards that can combine low-cost component fabrication, high-capacity coastal assembly and load-out access. That combination, not welding capacity alone, is what won Smulders this contract.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.
- Article status
- Published · Version 1
- Source date
- 17 November 2026
- MetalMate publication
- 17 November 2026
- Verification
- Automated evidence checks; not human reviewed
Smulders to Build Jacket Foundation for TenneT's LanWin Beta Offshore Platform — OffshoreWIND.biz