Projects & Demand / Europe · Asia ex-China · Netherlands · Germany · Singapore · Belgium Source 31 August 2026 ·
Heerema completes first 1,700-tonne roll-up for IJmuiden Ver Beta jacket
OffshoreWIND.biz reports that Heerema Fabrication Group completed the first structural element for TenneT’s 2 GW IJmuiden Ver Beta transformer-platform jacket at Vlissingen and performed the project’s first roll-up, lifting the 1,700-tonne steel element vertically with two cranes.
Fabrication began with first steel cutting in September 2025. Heerema is building the jacket under the GE Vernova–Seatrium consortium, which was contracted by TenneT for converter platforms including IJmuiden Ver Beta, IJmuiden Ver Gamma and Nederwiek 2.
MetalMate summary of the linked evidence
WHY IT MATTERS
Commercial context
Analysis: The milestone demonstrates progress from initial steel cutting to heavy structural assembly and confirms active offshore jacket work at Heerema’s Vlissingen yard. The wider three-jacket scope provides visibility for large-scale offshore steel fabrication.
MetalMate analysis
KEY DETAILS
The completed component is the first structural element of the IJmuiden Ver Beta jacket foundation, according to OffshoreWIND.biz.
The first roll-up moved a 1,700-tonne steel element from horizontal to controlled vertical orientation using two cranes.
Heerema Fabrication Group is building three jackets outsourced by the GE Vernova–Seatrium consortium.
Vattenfall and Copenhagen Infrastructure Partners previously said the related wind farm would be developed in two 1 GW phases, targeted for completion in 2029 and 2032.
WHAT TO WATCH
Outlook: Monitor subsequent structural assembly milestones and whether the phased 1 GW completion targets for 2029 and 2032 remain on schedule.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.