The two BC-Wind announcements that arrived within three weeks of each other look like separate procurement milestones. Read together, they are the clearest signal yet of where Poland's offshore wind supply chain actually stands: capable of fabricating and assembling turbine towers for 15 MW-class machines, but only at the assembly end of the value chain, with the heaviest steel — monopiles, transition pieces and the offshore substation — arriving by ship from somewhere else.
What was actually agreed
On 18 November 2026, Windar Polska and Siemens Gamesa signed an agreement covering 26 complete steel towers for the SG 15-236 turbines at Ocean Winds' 390 MW BC-Wind project in the Polish Baltic. The towers will be manufactured and assembled at Windar's Szczecin plant, with the scope extending beyond rolled and welded cans to internal platforms, ladders and high-voltage cable guides. Local subcontractor KK-Wind, also of Szczecin, supplies the low-voltage platforms.
Three weeks earlier, on 28 October, the first monopiles for the same project were discharged at the Świnoujście Offshore Terminal, operated by ORLEN Neptun (ORLEN Group) and leased by Ocean Winds from September 2026 through Q4 2027. The project needs 27 monopiles — 26 for turbines, one for the offshore substation — each roughly 9.5–10.5 m in diameter and 66–89 m long, with matching transition pieces.
| Element | Detail | Timing |
|---|---|---|
| Turbine towers | 26 × SG 15-236, Windar Polska (Szczecin) | Delivery from Q1 2028 |
| Monopiles | 27 (26 turbine + 1 OSS), stored at Świnoujście | Installation end-Q1/Q2 2027 |
| Transition pieces | 26 + OSS, installed by Seaway7 (reported) | Q3–Q4 2027 |
| Turbine installation | Cadeler, O-class vessel, from Terminal T5 Gdańsk | From Q2 2028 |
| Foundation installation | DEME Orion | 2027 |
The Szczecin plant is the story, not the order
Twenty-six towers is a modest order against the plant's nameplate. Windar's own project literature has quoted annual capacities ranging from 100 to 150 towers (or roughly 500 tower sections), supported by a PLN 653 million investment with PLN 230 million of Polish state aid, and up to 450 direct jobs. The discrepancy between the 100- and 150-tower figures appears to reflect different production configurations or phases rather than a contradiction in the underlying design; either way, BC-Wind alone will not fill the Szczecin line.
That matters for how the contract should be read. It is best understood as a qualification event rather than a volume event. Producing towers for the SG 15-236 requires the plant to demonstrate serial capability on sections of up to roughly 450 tonnes, 10 m diameter and 50 m length — the dimensions Windar specified when it announced the investment. The plant's groundbreaking took place in May 2025 with production planned from 2026, leaving a tight ramp before first tower deliveries in early 2028. A successful BC-Wind campaign gives Windar a reference for the wider Baltic pipeline; a slippage would be felt directly in the project schedule, since towers are on the critical path for a Q2 2028 installation start.
The structural weakness in the Polish position is the tower itself. As a rule of thumb, a 15 MW-class offshore tower weighs on the order of 800–1,000 tonnes across its sections, against perhaps 1,500–2,500 tonnes for a large monopile of the dimensions described here. Roughly speaking, the 26 towers represent something like 20,000–26,000 tonnes of fabricated steel (analysis; derived from typical per-tower weights, not published project figures), while the 27 monopiles and their transition pieces represent substantially more. Almost none of that heavier tonnage is being made in Poland for this project.
Świnoujście: port capability, not fabrication capability
The Świnoujście milestone is genuinely significant — Ocean Winds describes it as the first time Polish port infrastructure has handled a foundation delivery of this scale — but it is a logistics achievement. Poland's first dedicated offshore wind installation terminal, launched in June 2025, has now proven it can receive, store and internally transport 89 m monopiles on SPMTs. The local content generated is services: Dynpap (Szczecin) for monopile and transition-piece handling, Team Project (Modrzewie) for ground works and surface maintenance, MAG Offshore (Gdynia) supplying protective steel plates for SPMT movements.
That is a real supply chain, but a shallow one. The steel in those monopiles was rolled and welded elsewhere, and the offshore substation is being built by CRIST Offshore. Poland is capturing port operations, minor fabrication and assembly labour — not heavy foundation manufacture.
Manufacturing geography is bifurcating
The project's logistics reveal a deliberate split. Foundations stage through Świnoujście in the far north-west, close to the site some 23 km offshore. Turbines will be installed from Terminal T5 at the Port of Gdańsk, roughly 92 km (50 nautical miles) from the site, in the east. Towers, meanwhile, are built in Szczecin, between the two. Three Polish ports, three different roles, and a set of road and sea movements that will need careful sequencing in 2027–2028.
For steel and heavy-fabrication suppliers, the practical question is whether this split becomes the template for Poland's next round of projects. The country's offshore build-out is a multi-gigawatt programme; if towers are the only large steel structures localised, the domestic content of each project will remain in the low tens of percent by tonnage, regardless of how many Polish companies appear in the contractor lists.
What to watch
- Windar's ramp-up. Whether tower section production at Szczecin reaches serial output during 2027 determines whether Q1 2028 delivery and a Q2 2028 Cadeler installation start are credible.
- Foundation fabrication sourcing. No Polish fabricator has yet been identified for BC-Wind's monopiles or transition pieces. Awarding even a partial scope domestically on the next project would be a more meaningful localisation signal than any tower contract.
- Transition-piece installation. The reported Seaway7 scope for 26 TPs plus the offshore substation, scheduled for Q3–Q4 2027, is the next logistics test for Świnoujście.
- Contract values. The three DEME contracts (monopiles, inter-array and export cables) have been reported in the €150–300 million range by trade press; Windar's tower contract value is undisclosed. Neither figure has been confirmed at primary-source level here.
BC-Wind is Ocean Winds' first Baltic project and one of Poland's flagship builds. Its supply chain shows a country that has built the ports and the assembly capacity faster than it has built the steel mills and welding halls behind them — and 2027 will show whether that gap is closing or being designed in.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.