The headline fact is small: 21 monopiles and a first batch of turbine towers are now sitting at Akita Port, waiting for offshore construction to begin in spring 2027. The more consequential fact is buried inside it. Some of those monopiles were rolled, welded and painted in Japan — at JFE Engineering's Kasaoka plant in Okayama Prefecture — rather than imported from Europe, China or Southeast Asia.
That makes Oga–Katagami–Akita the first Japanese offshore wind farm to use domestically produced monopile foundations, according to JFE Engineering (a company claim, self-certified as "based on our own research"; no independent regulator confirmation was found). For a country that has spent a decade assembling an offshore wind policy framework while importing almost every structural component, it is the first tangible evidence that the localisation strategy is producing steel, not just roadmaps.
The core numbers
| Parameter | Value |
|---|---|
| Capacity | 315 MW, 21 × Vestas V236-15.0 MW |
| Location | Off Oga, Katagami and Akita cities, Akita Prefecture |
| Developer | Oga Katagami Akita Offshore Green Energy LLC (JERA Nex bp, J-POWER, Tohoku Electric Power, Itochu) |
| Monopile max weight / length / diameter | ~2,000 t / ~80 m / 10.5–11 m |
| Transition piece | ~500 t, 9.6 m diameter, ~26 m |
| Total foundation steel | ~43,000 t (SM520C grade) |
| Foundation manufacture | JFE Engineering, Kasaoka Monopile Factory |
| Foundation installation | Kajima (main contractor), Penta-Ocean CP-16001 SEP |
| Turbine installation | Japan Offshore Marine (DEME/Penta-Ocean), jack-up Sea Challenger, H2 2027 |
| Commercial operation | Mid-2028 |
The steel intensity is the figure worth carrying away: roughly 137 tonnes of foundation steel per megawatt, or about 2,048 t per turbine position. That ratio is itself a market signal. For every gigawatt of Japanese bottom-fixed offshore wind built on monopiles, the structural steel requirement is on the order of 130,000–140,000 tonnes of heavy plate — the kind of volume that justifies a dedicated plant only if the project pipeline is real.
JFE's Kasaoka facility, operational since April 2024 inside JFE Steel's West Japan Works, is designed for stable output of around 50 ultra-large monopiles a year at up to ~2,500 t each, with the capability to handle diameters up to ~12 m and plate thickness to 130 mm. The project's 100 mm plate and 10.5 m diameter sit comfortably inside those limits — deliberately so, since the plant was specified around the emerging Japanese turbine class rather than legacy European dimensions.
Why the contract chain matters more than the delivery
The delivery itself is a logistics event. The procurement structure around it is the interesting part, because it shows how Japanese contractors are being knit into the offshore supply chain in layers.
- October 2025: developer signs with Kajima for manufacture, procurement, transport and installation of foundations.
- December 2025: JFE Engineering receives the foundation manufacturing and transport order from Kajima (21 monopiles plus 21 transition pieces, production window January 2026–March 2027).
- August 2026: first domestically made monopile marked at a ceremony attended by METI/ANRE, MLIT and local officials — a state-visible milestone, not a private one.
- September 2026: first monopiles arrive at Akita Port; 29 October 2026: first turbine towers arrive.
- 13 November 2026: JFE Engineering and Akita Maritime Service win a five-year (extendable to full project life) balance-of-plant inspection and maintenance contract covering monopile foundations, subsea cables, onshore substation and transmission lines.
That last contract deserves more attention than it has received. It is the first long-term BOP O&M award for a bottom-fixed project selected under Japan's Sea Area Utilization Act, per JFE. What it does is lock a domestic industrial player into the operating phase as well as the build phase — a very different commercial position from a one-off fabrication order. It also formalises a local entity: Akita Maritime Service, founded in April 2023 by eight Akita organisations and now holding eleven shareholders including three fisheries cooperatives and several regional construction and electrical firms. O&M is where fisheries coexistence agreements, local content politics and long-run cost control actually get resolved, and the contracting structure reflects that.
The localisation picture is partial
It would be easy to over-read the monopile milestone. Three limits are worth stating plainly:
- Towers are not established as domestic. The tower arrival is confirmed, but the supplier was not identified in the sources reviewed. Japan has tower fabrication capacity (including Vestas' own Campbeltown-style arrangements elsewhere and domestic fabricators such as Japan Steel Works and others), but whether these 15 MW-class towers were imported or built locally is unconfirmed. Readers should not assume local content.
- Installation remains heavily foreign-supplied. The 21 turbines will go in on DEME's Sea Challenger, operated by Japan Offshore Marine, the DEME–Penta-Ocean JV, in H2 2027. The vessel was upgraded from a 900 t to a 1,600 t crane, widened and given longer legs, and transferred into JOM ownership with Japanese flagging targeted by FY2027. That is a real localisation step, but the engineering know-how and marine spread remain substantially European. Foundation installation uses Penta-Ocean's CP-16001 (1,600 t, jointly owned with Kajima and Yorigami Maritime) — domestic hull, imported practice.
- One plant is not a supply chain. Kasaoka's ~50 monopiles per year is meaningful against a pipeline of a few hundred megawatts annually, but Japan's stated offshore targets imply a build rate several times higher. Whether Kasaoka can compete on cost against Korean, Chinese and European fabricators once the protected early-round projects are exhausted is unproven.
The strategic read
The genuinely important question is not whether Japan can make a monopile — it clearly can now — but whether the domestic cost base can survive exposure to international competition as the sector scales. Japan's early offshore rounds have been structured so that developers can absorb higher domestic content costs. That cushion will thin. The Kasaoka plant's viability therefore depends less on Oga–Katagami–Akita than on the next several projects: if the pipeline materialises at scale, JFE has a first-mover position in a market where transport of 2,000 t, 80 m structures across the Pacific is expensive and slow; if the pipeline stalls, an underutilised ultra-heavy fabrication line becomes a stranded asset.
For steel producers, the immediate signal is that the heavy-plate demand story in Japanese offshore wind is now physical rather than forecast. Roughly 43,000 t of SM520C plate for one 315 MW project — and JFE Steel's proprietary J-TerraPlate, designed to cut weld length — is a modest volume against Japan's total plate output, but it sits in exactly the high-value, technically demanding segment where Japanese mills have been losing ground to Korean rivals. Offshore wind foundations are a defensible niche: thick plate, tight flatness, weldability at 100 mm, and just-in-time delivery to a yard that must then ship to a specific port within a narrow weather window.
The Oga–Katagami–Akita project's real significance, then, is not the September delivery or the October tower arrival. It is that Japan has now demonstrated an end-to-end domestic path — plate, fabrication, port logistics, installation vessel ownership, and long-term O&M — for a single project. Repeating it at scale, at competitive cost, is the open question.
References
- OffshoreWIND.biz, "First Monopiles, Turbine Towers Delivered for 315 MW Japanese Offshore Wind Farm Ahead of 2027 Construction," 16 November 2026.
- JFE Engineering, "Japan's first Order received for domestic monopile production for large-scale offshore wind power project in general waters," 26 December 2025.
- JFE Engineering, "国内初、着床式洋上風力発電ラウンド案件向けBOP設備の長期定期点検・維持管理業務を受託," 13 November 2026.
- JFE Engineering, "国内初、洋上風力発電向け基礎「モノパイル」国産初品が完成" (PRTIMES), 26 August 2026.
- Oga Katagami Akita Offshore Green Energy LLC, Project Overview; Construction Progress; contract notices of 23 October 2025 and 7 September 2026.
- Penta-Ocean Construction, update on Sea Challenger charter, 28 May 2026.
- Vestas, "Vestas wins 315 MW offshore order in Japan," 2024.
Source & methodology +
MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.
- Article status
- Published · Version 1
- Source date
- 16 November 2026
- MetalMate publication
- 16 November 2026
- Verification
- Automated evidence checks; not human reviewed