What was actually decided

On 5 November 2026 Ofgem published a notice under regulation 21(1) of the Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015 appointing a preferred bidder for the Dogger Bank B OFTO project — the sole qualifying project in Tender Round 11 (TR11). The winner is the consortium of Diamond Transmission UK (DTUK), wholly owned by Global Infrastructure Partners (now part of BlackRock), and Chubu Electric Power of Japan. The consortium announced the appointment on 10 November.

The scope is the full HVDC link between the 1.2 GW Dogger Bank B wind farm, roughly 130 km off England's east coast, and the National Grid: subsea cables, onshore cables, an offshore converter platform and an onshore converter station. Under the OFTO model the consortium buys the transmission assets from the generator after commissioning, is granted a 25-year transmission licence, and earns a regulated revenue stream for availability and performance.

Preferred-bidder status is not completion. It triggers a period in which funding, contractual and operational conditions must be satisfied before licence grant and transfer — the same sequence that has historically slipped by months rather than weeks.

The valuation gap is a category error, not a premium

Most coverage has picked up the consortium's "approximately £1 billion" and moved on. That figure sits alongside two quite different Ofgem numbers, and the distinction matters for anyone trying to infer competitive tension in TR11.

MetricFigureSource / nature
Consortium's stated asset value£1.0bn (€1.2bn)DTUK/Chubu release — its own characterisation
Ofgem TR11 project page estimate~£0.8bnRegulator's estimated transmission asset value
TR11 EPQ / shortlist notice initial transfer value£919.3mPre-tender regulatory estimate (index-derived; not directly verified in the PDFs)
Ofgem January 2024 launch-event description"approximately £1 billion"Earlier market-facing estimate

These are not competing bids. Ofgem's figures are estimates of transfer value set before the tender to size the opportunity; the consortium's ~£1bn is its own valuation at award. Notably, Ofgem's own launch material in early 2024 used "approximately £1 billion" before the shortlist notice settled on £919.3m — so the "gap" is partly Ofgem's own revision, not a bid above estimate. No source I reviewed discloses the winning bid price, and the R21(1) notice is a short appointment notice rather than a price disclosure. Readers should resist reading a 9–25% premium into figures that measure different things at different dates.

Why this asset is harder than the average OFTO

Dogger Bank B is an HVDC link, not the HVAC radial cables that made up most of the early OFTO rounds. That changes the operating risk profile materially: converter stations add power-electronics availability risk, spare-parts and specialist-vendor dependency, and a failure mode (converter outage) that can strand the full 1.2 GW rather than degrade it. Subsea HVDC export cables at this length are also harder and costlier to repair than shorter HVAC arrays.

For an availability-based, 25-year regulated asset, the practical consequences are in the O&M contract architecture and insurance, not the headline price. This is precisely the capability Chubu says it wants: its release frames Dogger Bank B as a way to "accumulate expertise in HVDC transmission technology and in the operation and maintenance of subsea transmission assets," explicitly to support offshore wind build-out in Japan and elsewhere.

DTUK's consolidating position

On the consortium's own numbers, DTUK will operate eleven UK OFTOs after transfer, with almost 7 GW of capacity and more than £5.5bn of transferred asset value. Arithmetic on those figures (my calculation) puts Dogger Bank B at roughly 17% of portfolio capacity and about 18% of transferred value — a meaningful but not transformative increment.

The more interesting signal is structural. UK offshore transmission is consolidating into a small number of infrastructure platforms — DTUK/GIP, Transmission Capital, and consortia built around utilities and contractors such as the Gravis–ORIX–UKPN Services and EKITD groups shortlisted in TR11. Each round now looks less like an equipment or EPC contest and more like an infrastructure capital-allocation contest, with operators choosing partners for technical depth rather than construction capability. Chubu's role fits that template: capital is GIP's, technical credibility and Japanese market optionality are Chubu's.

For Chubu, Dogger Bank B is its third UK OFTO after Walney Extension and Hornsea 1, both alongside DTUK. That is a deliberate, repeatable pattern — a Japanese utility using UK regulated transmission as a low-risk training ground for capabilities it expects to need domestically as Japan's offshore wind programme moves into deeper water and, eventually, HVDC.

What to watch

  • Licence grant and transfer timing. Preferred-bidder appointments routinely slip; watch Ofgem's TR11 page for the licence-grant milestone, and note that the project page still showed "EPQ commenced" at the time of writing.
  • The actual bid price. If Ofgem or the consortium discloses it later, the comparison against the £919.3m initial transfer value will be the real measure of TR11 competition — not the £1bn headline.
  • Dogger Bank B commissioning. The OFTO revenue clock starts with availability, so turbine installation progress on phase 2 is a direct commercial variable for the consortium.
  • HVDC O&M contracting. Whether the consortium leans on the converter OEM for long-term service or builds in-house capability will indicate how seriously the partners are treating HVDC as a core competence rather than a one-off.

One naming caveat: Ofgem's shortlist notice and some trade coverage refer to the bidder as "Diamond Transmission Partners," while the consortium uses "Diamond Transmission UK." These appear to be the same bidding group under different conventions; no source explicitly reconciles them.

Source & methodology +

MetalMate separates original-source evidence from summary and analysis. Verify the original source before procurement, legal or engineering decisions.

Article status
Published · Version 1
Source date
10 November 2026
MetalMate publication
10 November 2026
Verification
Automated evidence checks; not human reviewed

Ofgem Names Preferred Bidder for Dogger Bank B Offshore Transmission Assets — OffshoreWIND.biz