Steelwind Nordenham has completed delivery of its full 34-monopile scope for the Baltica 2 offshore wind project, according to OffshoreWIND.biz. The order involved around 56,000 tonnes of processed steel.
MetalMate Intelligence · Published 1 October 2026
Photo source: Steelwind Nordenham via LinkedInCredit: OffshoreWIND.biz
WHAT HAPPENED
OffshoreWIND.biz reported that Steelwind manufactured and delivered all 34 monopiles under its Baltica 2 contract. The overall foundation package comprises 111 monopiles, with EEW Special Pipe Constructions delivering the remaining 77.
MetalMate summary of the linked evidence
WHY IT MATTERS
Commercial context
The milestone confirms completion of a sizeable offshore-wind steel order and shifts attention to the remaining foundation deliveries. Steelwind’s scope represents about 31% of the project’s monopiles by unit count.
MetalMate analysis
KEY DETAILS
Steelwind’s 34 monopiles used around 56,000 tonnes of steel, according to OffshoreWIND.biz.
The largest foundations were reported at approximately 102 metres long, up to 10.5 metres in diameter and as much as 1,884 tonnes each.
Baltica 2’s total foundation package comprises 111 monopiles.
EEW SPC is delivering the remaining 77 monopiles.
WHAT TO WATCH
Watch for progress on EEW SPC’s remaining 77 monopiles and subsequent completion of the full 111-foundation package. The exact date of Steelwind’s final shipment or completed delivery was not stated.