The Polish Baltic's largest offshore wind build has crossed its heaviest threshold. Heerema's Thialf has installed all 100 wind-turbine foundations — monopiles and transition pieces — plus the jacket substructures for both offshore substations at Bałtyk 2 and Bałtyk 3, completing the campaign in September 2026 after roughly four months of offshore work.
That milestone matters less for what it says about the past than for what it exposes about the present: the primary structural steel for these two 720 MW farms was ordered, fabricated and installed on a schedule that is now effectively closed. What follows is electrical, mechanical and commissioning work — plus a fabrication and installation sequence for the substructures' topsides that is the last major steel and heavy-lift chapter of the project.
The shape of the project
| Parameter | Bałtyk 2 | Bałtyk 3 |
|---|---|---|
| Capacity | 720 MW | 720 MW |
| Ownership | Equinor / Polenergia 50/50 | Equinor / Polenergia 50/50 |
| Distance to shore | ~37 km | ~22 km |
| Turbines | 50 × Siemens Gamesa SG 14-236 DD | 50 × Siemens Gamesa SG 14-236 DD |
| Foundations | 50 monopiles + 50 TPs | 50 monopiles + 50 TPs |
| Offshore substation | 1 topside + 1 jacket | 1 topside + 1 jacket |
| First power | 2027 (combined expectation) | 2027 (combined expectation) |
| Commercial operation | 2028 (combined expectation) | 2028 (combined expectation) |
Together the farms total 1,440 MW — the bulk of Poland's first-generation offshore programme, and among the largest single offshore developments under construction in the Baltic. The developers claim the output will serve more than two million households.
Who built what
The contracting structure is worth understanding because it explains why so little conventional steel tendering remains visible. The JV split the works into large turnkey or consortium packages awarded mostly in 2024:
| Package | Supplier | Approx. value | Status |
|---|---|---|---|
| 100 monopiles | Sif (Netherlands) | Not disclosed | Fabricated and installed |
| 100 transition pieces | Smulders–Sif consortium | ~EUR 328 m | Fabricated and installed |
| Two OSS EPC packages (topsides + jackets) | Iemants NV / Smulders (Eiffage Métal) | ~EUR 350 m combined | Jackets delivered and installed; topsides in outfitting |
| Transport & installation | Heerema Marine Contractors | Not disclosed | Foundation campaign complete; topsides pending |
| Onshore export cables | Enprom (Poland) | ~PLN 173 m | Separate, onshore scope |
Two points for anyone tracking this project from a supplier's perspective. First, the offshore substation contract — often the segment where tier-two structural fabricators find work — was awarded as turnkey EPC to a single group, Smulders/Iemants, which internally subcontracted between its own yards. Second, the T&I contract sits separately from fabrication, so Heerema's scope covers installation of monopiles, transition pieces, jackets and topsides rather than their manufacture.
The newest addition is Searenergy Poland, engaged by the JV for hook-up and commissioning of both offshore substations and commissioning support for all 100 turbines, including corrective maintenance on transition pieces out of the Łeba O&M base ahead of turbine installation. Contract value and signing date have not been disclosed publicly.
The steel has largely moved through the system
The manufacturing geography is instructive. The jackets were built at Smulders' Newcastle yard at Wallsend in the UK; final topside assembly and outfitting took place at Vlissingen in the Netherlands. Each topside is roughly 3,700 tonnes and, according to project reporting, each jacket around 3,500 tonnes — more than 7,000 tonnes of structural steel per substation when topside and jacket are combined. The monopiles, at 65–72 m long and 7.5–9.5 m in diameter, and the 100 transition pieces represent the larger steel tonnage by far.
For steel suppliers and fabricators, the practical conclusion is that the primary structural procurement at Bałtyk 2 & 3 is complete. There is no evidenced open package for monopiles, transition pieces or substation jackets. The two topsides are already built and in outfitting; remaining work on them is electrical, mechanical and commissioning-related, not primary steel erection. Any suggestion that transition-piece or jacket fabrication could still be tendered would contradict the record.
What does remain, and is worth watching cautiously, is speculative: operational repair or replacement work over the 2028+ operating life. No procurement has been announced for that, and it should not be treated as an accessible pipeline.
What happens next
The critical path now runs through the two substation topsides and the turbine installation campaign. Thialf is expected back for the Bałtyk 2 topside in winter 2026, with the Bałtyk 3 topside following in summer 2027 — an 18-month gap that reflects a staggered installation logic rather than delay, but one that pushes Bałtyk 3's commissioning window later. Turbine installation by Siemens Gamesa will follow the substation hook-ups, with first power targeted for 2027 and commercial operation for 2028 across both farms.
The sequencing risk is concentrated in the winter installation of the Bałtyk 2 topside — a heavy-lift offshore operation in the Baltic in a season not known for generous weather windows. Any slip there cascades into hook-up, turbine installation and the first-power date. For a programme that has so far met its foundation milestones on schedule, the topside lift is the next genuine test.
Why it matters
Bałtyk 2 & 3 are a template for how Poland's offshore build is being structured: large, fully scoped turnkey packages awarded to established Northern European fabricators and marine contractors, with a domestic developer (Polenergia) as co-owner and Polish firms holding onshore cable and commissioning roles rather than the heavy offshore steel. That structure delivered speed — foundations complete within months of the original plan — but it also means the steel value chain for this wave of Polish projects ran through Dutch, Belgian and UK yards rather than Polish ones. As Poland prepares its second-generation offshore round, whether that pattern changes is a question the domestic fabrication sector will be watching closely.