Berwick Bank B, the 1.4 GW second phase of SSE Renewables' 4.1 GW outer Firth of Forth development, now has preferred suppliers for both of its two largest offshore packages. What it does not yet have is a final investment decision, a fabricator for its foundations, or any published contract value.
That distinction matters more than usual in this project. Headlines describing Seaway7 and Siemens Energy as "selected" or "signed" overstate the commercial certainty: both arrangements are explicitly conditional, and SSE is targeting FID in late 2027, with offshore work starting the following year.
The project in brief
| Attribute | Detail |
|---|---|
| Developer | SSE Renewables (100%) |
| Location | Outer Firth of Forth, ~38 km east of the Scottish Borders coast |
| Total development | Berwick Bank, three phases, consented at up to 4.1 GW (SSE markets "up to 4.3 GW"; up to ~307 turbines) |
| This phase | Berwick Bank B, ~1.4 GW, fixed-bottom |
| Route to market | 20-year CfD won in Allocation Round 7 (announced January 2026) |
| Grid connections | Branxton (East Lothian) and Cambois/Blyth (Northumberland) |
| FID target | Late 2027 |
| Offshore construction | From 2028; foundations 2029; turbines/OSS 2030–2032 |
What has actually been awarded
Two preferred-supplier announcements, three weeks apart, define the current procurement position:
- Seaway7 (Subsea7's offshore wind EPCI unit), 20 October 2026 — engineering, procurement, construction and installation of wind turbine foundations and inter-array cables, covering design, supply and installation. Expressly subject to final contract award. A month later Seaway7 disclosed the intended vessel spread: Seaway Alfa Lift, Seaway Strashnov and Seaway Phoenix, deployed across 2029 and 2030.
- Siemens Energy, 11 November 2026 — wind turbines and offshore substation platforms, with the substations to be delivered in partnership with Smulders-HSM. Subject to FID and final contract award.
Neither announcement carried a contract value. For Subsea7, awards of this type are disclosed only above its internal threshold; the absence of a figure should be read as "undisclosed", not as a small package. The vessel disclosure is indicative scheduling — "expected to be deployed" — not a firm call-off.
Readers should treat Berwick Bank B as being in a conditional preferred-supplier stage, not a completed EPC award. The commercial weight sits with SSE until FID.
The steel question is still unanswered
For steel suppliers and fabricators, the October and November announcements resolve the delivery layer but not the fabrication layer. Seaway7 holds EPCI responsibility for the foundations; it has not named the yards that will roll the monopiles or transition pieces, and no steel mill or plate supplier has been identified.
A 1.4 GW fixed-bottom array at current turbine ratings implies on the order of 80–120 foundations, each involving several thousand tonnes of structural steel once monopiles, transition pieces and secondary steel are counted — a plausible order of magnitude of several hundred thousand tonnes across the phase, though no tonnage has been published and SSE has not confirmed foundation type. Whether the project uses XL monopiles or jackets is a decision that will sit with Seaway7's detailed design and will materially affect both the plate specification and the eligible fabrication yards.
The Siemens Energy/Smulders-HSM arrangement is the one place where a steel fabricator is already visible in the chain: Smulders-HSM will build the offshore substation topsides. That is a European yard booking, not a UK one, and the steel for those structures will be procured within that subcontract chain.
Secondary steel demand — boat landings, internal platforms, J-tubes, cable protection — will follow the foundation contract, not precede it. None of these packages should be treated as open opportunities today; they are contingent on FID and on Seaway7's subsequent subcontracting decisions, which are not evidenced.
The consent stack is now complete
The regulatory picture has filled in steadily and is, unusually, ahead of the commercial one:
- July 2025 — Scottish Government consent (Section 36 / marine licence) for the full three-phase project, including export cables to Branxton.
- November 2024 — Northumberland County Council approval for onshore infrastructure at Cambois (landfall, converter station, grid connection).
- January 2026 — Berwick Bank B secures its 20-year CfD in AR7 (SSE's own announcement is dated 22 January 2026).
- 9 November 2026 — MMO marine licence for the "Cambois Connection" export cable infrastructure in English waters for the third phase, covering up to four HVDC export cables and up to 1.8 GW of transmission capacity.
Phases A and C remain without a route to market and are expected to compete in future CfD rounds. Berwick Bank B is the only phase with both a revenue contract and named suppliers — which is why it carries the development's near-term schedule.
Why it matters beyond this project
Berwick Bank B is a useful bellwether for the UK offshore wind supply chain for three reasons.
First, its timing concentrates demand. Foundations in 2029 and turbines in 2030–2032 place it in the same window as several other UK and European projects reaching construction after the AR7 round, competing for the same installation vessels and the same fabrication slots. Seaway7 committing three vessels is an early signal that installation capacity is being reserved well ahead of FID.
Second, the conditional-award model is becoming normal. Preferred-supplier status allows developers to lock in capacity and pricing signals before committing capital, but it pushes risk onto contractors and their subcontractors, who must hold yard slots and vessel options without a firm order. For fabricators, this means capacity planning conversations start earlier and firm orders land later.
Third, the CfD-backed revenue gives the phase a credibility that its unconsented-for-market siblings lack. AR7 cleared a 1.4 GW phase at a strike price that has not been widely publicised; without the clearing price, the project's economics remain opaque from the outside.
What to watch
- Fabricator nomination by Seaway7 — the single most consequential unresolved item for steel suppliers. No timeline has been published.
- Final contract awards to Seaway7 and Siemens Energy, expected around FID in late 2027.
- Foundation type confirmation — monopile versus jacket, with direct implications for plate tonnage and yard selection.
- Any Subsea7 disclosure of contract value, which would give the first hard number on the EPCI package.
- Offshore preparatory works from 2028, the first physical evidence that the schedule is holding.
Caveats
Capacity figures vary between SSE's corporate page ("up to 4.3 GW", "almost 7 million homes") and the project microsite ("up to 4.1 GW", "over six million homes"); 4.1 GW is the consent figure and is used here. The historical BVG Associates supply-chain study cited by SSE — ~9,300 UK jobs at peak construction "in 2026" and £8.3bn GVA — is now materially out of step with the actual build programme and should not be relied on for current economic claims. Steel tonnage estimates above are the author's own order-of-magnitude analysis, not project data.