Vietsovpetro recorded first commercial oil from the BK-26 wellhead platform at the Bach Ho field (Block 09-1) on 9 November 2026 at 07:15, 36 days ahead of the 15 December 2026 date set by the bilateral Intergovernmental Council. The platform is operational. Read that correctly: BK-26 is not a new field development in the conventional sense. It is a brownfield add-on — a light, normally unmanned wellhead platform bridged to the existing MSP-8 platform — whose commercial significance lies less in its volumes than in what its delivery says about how Vietsovpetro intends to keep a mature field producing.
What was actually built
The project has four scope elements, and only the first is a new structure:
| Scope element | Status |
|---|---|
| BK-26 wellhead platform (jacket + topside), nine-slot design with roughly three spare slots | Operational |
| Connecting bridge BK-26–MSP-8 | Operational |
| Modification/upgrade of MSP-8 to receive and process BK-26 production | Operational |
| Relocation of the MSP8–MSP4 subsea power cable | Operational |
BK-26 does not add a processing train, living quarters or a new export route. Its production is sent across the bridge to MSP-8 for preliminary separation and then onward to the main processing platforms. The Vietnamese environmental impact assessment material describes the facility as "light, unmanned" — a low-weight, low-manning drainage node added to the existing hub rather than an independent production centre. The EIA also lists nine BK-26 development wells, with drilling spread across 2026–2028, so the facility will be progressively populated rather than brought to full well count at start-up.
Neither Vietsovpetro nor Petrovietnam has published a BK-26 plateau production rate or a reserve estimate. One EIA-derived figure of roughly 1,500 m³/day design liquid-handling capacity circulates in search summaries of the document; that is a processing envelope, not an oil-rate forecast, and should not be read as one.
The schedule: seven months from go-ahead to first oil
The pace of delivery is the most striking feature of the project.
| Date | Milestone |
|---|---|
| January 2025 | Detailed design and procurement of materials/equipment begin |
| 29 December 2025 | Notice to proceed with construction and installation |
| 24 April 2026 | Jacket fabrication complete; onshore acceptance |
| 17 May 2026 | Jacket installed offshore (23 days after acceptance) |
| 8 September 2026 | Topside and connecting bridge fabrication complete; onshore acceptance |
| 15 September 2026 | Topside installed offshore; hook-up and offshore completion |
| 3 November 2026 | Overall acceptance by the Vietsovpetro Acceptance Council |
| 5 November 2026 | Decision to put the project into use |
| 9 November 2026 | First commercial oil |
Roughly ten and a half months elapsed between the construction notice to proceed and first oil; the offshore campaign itself — jacket installation in mid-May, topside and hook-up complete by mid-September, first oil in early November — took under six months. For a brownfield tie-in with an intervening modification package on a live producing platform, that is fast.
The real story: vertical integration, not a third-party EPCI award
Vietsovpetro's own announcement frames the outcome as proof of "self-reliance across the whole EPCI chain — from geological study, field design and production drilling to detailed engineering, procurement, fabrication and offshore installation." No third-party EPCI award appears in the public record. The fabrication work was carried out at the Vietsovpetro yard in Vung Tau, and Vietsovpetro's own Construction and Installation Enterprise (Xí nghiệp Xây lắp) ran an internal emulation campaign to complete the BK-26 works.
One external fabrication contractor does appear in the public record. SREC, a Vietnamese engineering and fabrication firm, states in its own project listing that it managed and fabricated the BK-26 topside and connecting bridge for Vietsovpetro at the Vung Tau yard, giving a quantity of 1,200 t covering primary and secondary structural steel, deck plating, grating, stairs, handrails, supports and the bridge structure, completed in 2026. That page could not be retrieved during this research (repeated HTTP 404 responses), so the attribution and the tonnage rest on search-result summaries and should be treated as reported but unverified. If accurate, it suggests Vietsovpetro's in-house model includes subcontract fabrication capacity rather than being purely self-performed.
Steel: the numbers that are known, and the larger one that is not
Structural steel quantities for BK-26 are only partially in the public domain, and the pieces do not add up to a total platform weight.
| Structure | Reported steel quantity | Source status |
|---|---|---|
| Main jacket structural steel | 649 t | Petrovietnam trade union publication (petrotimes) |
| Transition piles | 794.41 t | Same source |
| Boat landing | 21.79 t | Same source |
| Temporary drilling deck | 23.25 t | Same source |
| Jacket-related temporary works structure (BPTC) | 279.52 t | Same source |
| Listed jacket-related items, subtotal | ~1,768 t | Derived by summation |
| Topside and connecting bridge | ~1,200 t | SREC project record (unverified) |
Two cautions apply. First, the ~1,768 t subtotal mixes permanent jacket structure with piles and temporary construction works — it is not a deliverable steel weight. Second, the 1,200 t topside figure is a contractor claim that could not be independently confirmed. Total steel for a nine-slot unmanned wellhead platform plus a bridge would plausibly sit in the several-thousand-tonne range on these figures, but no consolidated tonnage has been published.
Steel procurement for the platform structures is complete: every structural element is fabricated, installed and in service. The remaining steel demand associated with BK-26 is not structural but tubular — casing and completion strings for the development wells still to be drilled through 2028. That is a steady, multi-year requirement for OCTG rather than a milestone package, and its scale is not disclosed.
Why this matters beyond the tonnage
Bach Ho is a mature, water-flooded field. Vietsovpetro's own strategic language around BK-26 emphasises "small, marginal fields at optimised cost" and the value of drainage points that can be added incrementally to existing infrastructure. BK-26 is a template for that approach: light unmanned platform, bridge tie-back to a processing hub, minimal new process equipment, short offshore campaign, in-house EPCI. The 36-day schedule gain matters commercially because additional output supports Vietsovpetro's 2026 production target, but the more durable signal is the demonstration that the joint venture can execute a fast, low-capital brownfield add-on without external contracting.
For context on scale, Block 09-1 as a whole carried an estimated 2P oil resource of roughly 890 million tonnes at end-2025, with about 638 million tonnes remaining. Those are block-level figures and say nothing specific about BK-26.
What remains
The platform is in service. The outstanding work is the nine-well development drilling programme running through 2028 and the associated production ramp-up, neither of which has a published rate target. No BK-26-specific reserves or plateau figures should be assumed from the available public record.