What has actually been decided — and what has not

Ofgem's 5 November 2026 notice under regulation 21(1) of the Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015 appointed a consortium of Diamond Transmission UK (DTUK) and Chubu Electric Power as preferred bidder for the transmission assets of the 1.2 GW Dogger Bank B offshore wind farm, the second phase of the 3.6 GW Dogger Bank complex roughly 130 km off England's east coast.

The distinction matters more than the headline. A preferred bidder appointment is not a completed transfer. Two separate steps remain: the formal grant of the 25-year OFTO licence, and completion of the asset sale from the wind farm owners to the consortium. Neither has a published date. Until both close, SSE Renewables, Equinor and Vårgrønn retain ownership of the transmission system, and the consortium has no operational remit.

That sequencing is standard for the OFTO regime — the transmission link is built and energised by the generator, then transferred to a competitively tendered, Ofgem-licensed operator once construction risk is retired — but it is frequently elided in coverage that treats preferred bidder status as a handover.

The last major commercial variable: price

Reports of the asset's value have drifted over the tender's life, and none of the published figures is a confirmed transfer price.

Source / dateStated valueStatus
Ofgem, Tender Round 11 launch, February 2024~£1 billionReported via Ofgem transparency document; launch estimate
Ofgem TR11 EPQ shortlist notice, 18 July 2024£919.3 millionSecondary summary of the notice; not independently verified in the PDF
Ofgem TR11 project page (current)~£0.8 billion for 1,200 MWSecondary; page could not be retrieved directly
Consortium (via trade press), November 2026~£1 billionBidder's own characterisation, not an Ofgem figure

Ofgem's final determination of transfer value — the regulated asset base on which the OFTO earns its return — is the number that will actually govern the deal, and it has not been published. The gap between the roughly £0.9–1.0 billion early estimates and the ~£0.8 billion currently shown on Ofgem's TR11 material is worth noting: it may reflect scope or cost adjustments as the link was delivered, but that is inference, not stated fact.

For the wind farm owners, the transfer recovers capital sunk into transmission infrastructure they were never intended to own long-term. For the consortium, the acquisition is a low-risk, index-linked, availability-based revenue stream with no construction exposure — the classic infrastructure-investor profile.

Who won, and why the partner mix is the interesting part

DTUK is wholly owned by Global Infrastructure Partners (now part of BlackRock) and is one of the most established OFTO investors in the UK market. Chubu Electric Power, Japan's third-largest utility, brings transmission operations experience and HVDC know-how — and, significantly, a track record: Dogger Bank B would be its third UK offshore transmission investment alongside DTUK, following Walney Extension and Hornsea 1.

The consortium states that on completion it will operate eleven UK OFTO projects totalling almost 7 GW and more than £5.5 billion of transferred asset value. Those are the bidder's own figures, not Ofgem's, and should be read as such.

The 2024 shortlist shows what the tender was worth to the market: four groups reached the Invitation to Tender stage after Enhanced Pre-Qualification — Diamond Transmission Partners, the EKITD Consortium, the Gravis–UKPN Services Consortium, and Transmission Capital Partners. The UK OFTO pipeline remains one of the deepest pools of operational offshore transmission assets globally, and competition for it is consistently real.

How the transmission system was actually built

The "unresolved EPC contractor" question is best answered by recognising that Dogger Bank's transmission link was never a single-EPC job. It was procured as a set of discipline-specific contracts — a structure that had significant steel-sector consequences.

  • HVDC technology: Hitachi Energy supplied the HVDC Light systems across all six converter stations for phases A, B and C, holding overall design, engineering, procurement, construction and installation scope for the converter stations, including the two onshore stations at Creyke Beck near Beverley serving A and B.
  • Offshore converter platforms: Aibel was the EPCI contractor for the three topsides, one per phase. The Dogger Bank B topside was built at Aibel's Thai yard, then outfitted with Hitachi Energy's HVDC equipment at Haugesund, Norway, before sail-away in early April 2024.
  • Steel jacket foundation: designed and fabricated by Saipem.
  • Installation: Saipem's heavy-lift vessel Saipem 7000 installed the platform on 17 April 2024.
  • HVDC export cables: NKT under an EPCI contract confirmed in November 2019, covering roughly 4 × 175 km of 320 kV DC offshore cable and 4 × 32 km of 320 kV DC onshore cable, manufactured at Karlskrona, Sweden, and installed by NKT Victoria. At the time it was NKT's largest-ever XLPE power cable order.
  • Onshore civil works: Keltbray (now Aureos Infrastructure) on groundworks for the converter stations.

Steel: the fabrication window has closed

The steel content in the Dogger Bank B transmission scope — the Saipem-built jacket, the Aibel topside structure, rebar and structural steelwork at the Creyke Beck converter station — was fabricated and delivered before the platform was installed in April 2024. Primary steel procurement on this asset is complete. The jacket is on the seabed and the topside is in service.

Any remaining commercial activity around Dogger Bank B transmission is operational or ownership-related, not supply-related. Forward-looking steel demand attaches to other UK OFTO pipelines and to future phases within Dogger Bank (phase C uses Hitachi Energy HVDC and its own Aibel platform), not to a retrofitted opportunity here. Any suggestion of remaining steel scope on Dogger Bank B should be treated as unevidenced.

Where the programme stands

SSE reported that Dogger Bank B achieved first power in early March 2026, with 20 turbines installed at reporting. The offshore converter platform is installed and energised; the export cables are laid; the onshore converter stations are in service. This is consistent with the transmission assets being genuinely operational well before the commercial transfer to the OFTO concludes — the regulator's tender clock and the wind farm's construction clock are decoupled by design.

A large steel offshore transformer platform on a barge being towed across Belfast Lough, with green hills in the background.
An offshore transformer platform under tow in Belfast Lough — illustrative of the heavy-lift transport and installation logistics that delivered Dogger Bank B's converter platform in April 2024. This is a different project and does not show Dogger Bank B.Credit: Ross · CC BY-SA 2.0 · Illustrative, not a photograph of this project · source

What to watch

The two dates that matter are the licence grant for Dogger Bank B and financial close on the acquisition. When they arrive, Ofgem will publish the determined transfer value, which will put paid to the £0.8bn versus £1bn ambiguity and establish the regulated asset base the consortium will earn on for 25 years. Until then, treat preferred bidder status as a signal of competitive outcome and creditworthiness, not as a completed transaction — and treat the Dogger Bank B transmission system as an operating asset whose construction supply chain has already been paid out.