Germany's offshore wind build-out has entered a phase where developers pay for the seabed and then must make the economics work without a state-backed revenue guarantee. Dreekant, EnBW's 1 GW project on site N-12.3 in the North Sea, is one of the clearest examples of that model — and a recent engineering award has quietly locked in two of the decisions that matter most to the steel and fabrication supply chain: the foundation type, and who gets to design it.
What Dreekant actually is
| Attribute | Detail |
|---|---|
| Name | Dreekant (Low German for "three edges," from the triangular site shape) |
| Site designation | N-12.3 |
| Capacity | 1,000 MW, 100% EnBW-owned |
| Location | German EEZ, North Sea, ~120 km northwest of Heligoland |
| Site area | ~80 km² (triangular) |
| Water depth | 37.9–45.6 m |
| Mean wind speed | 10.6 m/s |
| Foundations | Monopiles (confirmed) |
| Grid connection | 66 kV direct connection to TenneT's LanWin5 / NOR-13-1 converter |
| Permitting application | Planned 2027 |
| Final investment decision | Targeted 2029 |
| Commissioning | 2032 per current EnBW materials |
The project traces back to June 2024, when the Bundesnetzagentur concluded auctions for two non-centrally pre-investigated North Sea sites totalling 2,500 MW. EnBW Offshore Projektgesellschaft 1 GmbH won N-12.3 with a bid of €1.065 million/MW — €1.065 billion in total. The sister site N-11.2 went to Offshore Wind One GmbH at €1.305 million/MW (€1.9575 billion), bringing combined auction proceeds to roughly €3.02 billion.
Two features of that auction matter for how the project will be built out.
First, N-12.3 attracted seven zero-cent bids, which under Germany's Offshore Wind Energy Act triggers a dynamic bidding procedure. N-12.3 required 55 bidding rounds before EnBW prevailed. The winning contribution is paid in equal annual instalments to the connecting transmission system operator over 20 years, starting once the wind farm is operational — from 2031 under the original schedule. Marine-conservation contributions go to the federal budget within a year.
Second, because the site was not centrally pre-investigated, the developer holds the site right and funds the contribution, while the transmission system operator provides the grid connection assets. That is the structural reason Dreekant has no subsidy line item — and the reason its cost discipline, foundation optimisation and installation strategy carry unusual weight.
The engineering chain is forming, but only the front end
Dreekant has now assembled a design bench, but not a supply chain.
JBO (Jörss–Blunck–Ordemann) was awarded geotechnical expert work and pre-FEED design in November 2024. JBO's pedigree here is direct: it previously delivered detailed foundation design for EnBW's He Dreiht, Germany's largest offshore wind farm and itself built without state funding. JBO's offshore scope spans FEED studies, foundation concept development, pre-dimensioning, integrated load calculations incorporating soil and environmental effects, and verification of geotechnical, structural and grouted-connection performance.
SLPE was then awarded the next, larger tranche: concept design, FEED and detailed design of the wind turbine foundations, plus support during fabrication, installation and commissioning. SLPE announced the award on 22 September 2026, with trade coverage following on 23 September. SLPE is UK-based (London head office, Bristol office) and part of the Smulders group — a detail worth noting, since Smulders is itself a major steel fabrication group active in offshore wind.
Joseph Hilton, SLPE's Managing Director, framed the award as a significant milestone for the firm. SLPE has cited its Inch Cape work in Scotland — concept design followed by a 2021 detailed design contract — as the closest analogue to the Dreekant mandate. Its technical toolkit includes monopile and transition-piece design, geotechnical and primary structural engineering, and a proprietary monopile optimisation tool, MonoPoly.
What this award is not: it is an engineering services contract. No monopile fabricator, steel mill or installation contractor has been announced.
Monopiles over soft ground — the decision that shapes the steel order
EnBW has completed ground investigations at Dreekant and confirmed the foundation type. Geoquip Marine Operations AG carried out cone penetration tests to establish seabed bearing capacity and composition, preceded by geophysical surveys to rule out unexploded ordnance before borehole work.
The critical finding, in the words of EnBW Dreekant project manager Markus Lapke: the data is essential for planning the foundations, and EnBW is "pleased that it is possible to use monopiles as foundations despite the soft top soil layers."
That sentence carries more commercial weight than it might appear to. Soft upper sediments generally push designers toward greater embedment depth to mobilise adequate lateral resistance, which tends to increase monopile length and, with it, steel tonnage. Had the ground been poor enough to rule out monopiles, the project would have been looking at jackets or suction-bucket concepts, with a very different fabrication market, cost profile and installation vessel requirement. EnBW's confirmation that monopiles remain feasible is, in effect, the design lock-in that lets SLPE optimise rather than re-scope.
No steel grade, plate thickness, monopile diameter, wall thickness or tonnage has been published. Those numbers will emerge from the detailed design phase, and they will depend on the turbine choice — which is also still open. EnBW lists the turbine type as not yet determined. The current factbook describes the foundations as bottom-fixed monopiles with commissioning in 2032/33.
For steel producers and fabricators, the practical takeaway is timing. Detailed foundation design is now under way with SLPE, but the fabrication package typically follows later in the development cycle, after FID. With FID targeted at 2029, the procurement wave for monopile steel is more likely a late-decade event than an imminent one.
An installation-technology thread worth watching
One adjacent development suggests EnBW is already thinking about how these monopiles will go into the ground. In April 2026, IQIP reported that EnBW, together with Vattenfall, was enabling a full-scale offshore demonstration of EQ-Piling technology for monopile installation, and that announcement linked the demonstration to EnBW's Dreekant development.
The relevance is noise. Conventional impact piling generates high underwater noise levels and often requires mitigation — big bubble curtains or similar — which adds cost and vessel time. If a quieter installation method can be proven at full scale, it changes the installation logistics envelope for projects like Dreekant, where water depths of 38–46 m and a ~170 km distance to the Lower Saxony landfall already make marine operations expensive.
Grid connection: the TSO side is further along than the wind farm
The transmission side of Dreekant has its own supply chain, and it is more advanced. TenneT identifies LanWin5 / NOR-13-1 as the 2 GW grid connection serving the N-12.3 area, with a planned completion date of 30 September 2032. That 2 GW capacity comfortably accommodates Dreekant's 1 GW.
In July 2026, Hitachi Energy and Larsen & Toubro were announced as the LanWin5 awardees — Hitachi Energy supplying HVDC technology and L&T acting as EPC and manufacturing partner for the transmission infrastructure. The Dreekant wind farm will connect into this system via a 66 kV direct connection to the offshore converter.
This matters because it decouples two timelines. The wind farm's commissioning depends on the converter being ready; the converter has its own contracted supply chain, its own steel content (platform structures, HVDC equipment housings) and its own delivery risk. A slip in LanWin5 constrains Dreekant regardless of how well the foundation package progresses.
Timeline drift: read the dates carefully
Dreekant's published schedule has moved, and the movement is instructive rather than alarming.
| Milestone | Earlier EnBW communications (2024) | Current EnBW materials (2025–2026) |
|---|---|---|
| Permitting application | Not specified | 2027 |
| FID | 2028 (2024 Factbook) | 2029 |
| Commissioning | 2031 | 2032 (2032/33 in 2025 Factbook) |
The pattern — FID slipping from 2028 to 2029, commissioning from 2031 to 2032 — is consistent with a project still in design and permitting development rather than one in execution. It also reinforces that the current engineering awards are front-end work: studies, concepts and detailed design that must be completed before a sanction decision is credible.
The 2027 permitting application is the next hard, externally observable milestone. EnBW's FY 2024 investor presentation already noted approval-document work had begun, which aligns with a 2027 filing.
What remains genuinely unknown
It is worth being explicit about the gaps, because a great deal of Dreekant is still undefined:
- EPCI contractor: no engineering, procurement, construction and installation contractor has been identified.
- Fabricator: no monopile manufacturer named; no steel supplier named.
- Turbine supplier and model: EnBW states the type as not yet determined, with the OEM unidentified.
- Foundation quantities and dimensions: number of turbines and foundations, monopile diameters, lengths, wall thicknesses and total tonnage all unpublished.
- Steel specification: no grades or plate specifications disclosed.
- Approval submission content: the permitting application is planned for 2027 but details are not public.
- Whether the 2029 FID holds: it is the current stated target, not a commitment.
Why it matters
Dreekant sits at the intersection of three trends that will define the German North Sea for the rest of the decade.
The developer-pays model is now the default for new German sites. EnBW committed roughly €1.065 billion for the right to develop N-12.3, payable over 20 years from operation. Every subsequent engineering decision — foundation type, turbine size, installation method, steel tonnage — is a lever on whether that outlay can be recovered at market power prices. That is why the monopile confirmation matters: it is the lowest-cost, most manufacturable and most installable foundation family at these water depths, and keeping it in play preserves the widest possible supplier base across Europe.
The foundation design bench is consolidating around proven partnerships. JBO's role builds directly on He Dreiht; SLPE's role builds on Inch Cape. Both are being reused for the same reason: on projects with no revenue subsidy, design risk is expensive risk, and prior working relationships with the same client or comparable sites reduce it.
The steel order is still ahead, not behind. For fabricators, plate mills and coating and welding suppliers watching the German pipeline, Dreekant is a project to track through the 2027 permitting milestone and the 2029 FID gate — not one to quote today. When the monopile package eventually comes to market, it will be shaped by SLPE's optimisation work, by the water depths and soft-soil embedment requirements at N-12.3, and by whatever turbine EnBW selects. None of those three inputs is fixed yet, and that is precisely why the next 18 months of design work will determine the size of the prize.