East Anglia Two (EA2) is no longer a permitting story. The 960 MW project, developed by ScottishPower Renewables (Iberdrola Group) some 33 km off the Suffolk coast in the southern North Sea, has a Contract for Difference from Allocation Round 6 (963.07 MW at £58.87/MWh in 2012 prices, delivery 2028/29), a final investment decision behind it and an investment figure of roughly £4 billion. What matters now is delivery: foundations are in fabrication, the offshore substation is under construction, the installation vessel has been delivered, and the survey campaigns that bracket offshore work are being booked.

For steel-sector readers the interesting question is narrower than the project's headline numbers. EA2 is a large, near-term order for offshore wind monopiles and transition pieces — but the public record on the heavy plate that goes into those structures is thin, and some of what circulates as "EA2 steel supply" is not what it appears.

The structural scope, and who is building it

EA2 uses 64 Siemens Gamesa SG 14-236 DD turbines on monopile foundations. The fabrication and installation packages have all been awarded; the commercial window for primary structure supply has closed.

PackageSupplierScopeStatus
Monopiles (64)Sif Holding, Maasvlakte 2, RotterdamFabrication and load-outAwarded Oct 2024; production scheduled from H2 2026
Transition pieces (64)Sif–Smulders JVPrimary steel at Sif Roermond (NL), outfitting at Smulders Hoboken (BE)Awarded Oct 2024
Offshore substationHSM Offshore Energy (EPCIC), with Iv for engineering/procurement/integration~5,100 t topside (Stormpolder, NL), ~3,450 t jacket (Smulders HSM, River Tyne)EPCIC awarded early 2025; construction started March 2026
Foundation and turbine T&ICadeler64 monopiles and 64 WTGsFirm contracts signed Nov 2024, ~€360–382 m; offshore works from 2027

The foundation award went through a capacity reservation that Sif had already booked as a 140-kilotonne entry in its 2026 order book before converting it to a firm contract (taking its 2026 firm order book to 210 kt). That 140 kt is an order-book reservation covering the EA2 scope — it is not a published monopile tonnage. Scaling from Sif's reference XXL monopile (~120 m, ~11 m diameter, ~2,500 t) across 64 units would suggest something in the region of 130–160 kt, but that is my estimate, not a disclosed figure. The underlying design parameters are also not public in final form; ScottishPower's project description for the consent envelope cited indicative monopile diameters of roughly 13–15 m and embedment up to about 45 m.

What the steel record actually shows — and what it does not

Two steel-supply claims circulate around EA2. They should be read very differently.

Stahlwerk Thüringen (SWT): real, but small. The German long-products producer states it supplied 120 tonnes of "SWT Green Steel" for East Anglia Two in S355MLO, S355K2+M and S355J2+M grades, under its lower-CO2 EPD route (~335 kg CO2e/t). This is a genuine, named, quantified EA2 steel supply. It is also, against a 960 MW project, almost certainly secondary or ancillary steel rather than monopile shell plate — and it should not be presented as evidence of the project's primary steel sourcing.

Dillinger: a plausible lead, not a confirmed EA2 supplier. Sif's 2024 annual report records a Sif–Dillinger agreement on monopile circularity, which places Dillinger in Sif's plate supply chain. Neither company has been found stating that Dillinger plate is going into the EA2 monopiles specifically. Readers tracking the heavy-plate question should treat Dillinger as the strongest lead available, and nothing more.

No public source located for this article names the EA2 monopile plate mill, the plate grades (for example S420ML or S460ML) or the plate tonnage. That gap is a reasonable commercial inference in itself: with monopile fabrication already ramping at Maasvlakte 2 and production scheduled to start in H2 2026, the plate buying for the foundation programme will have been largely settled inside Sif's procurement, well away from public view. Anyone hoping to sell heavy plate into EA2's monopiles is, on the available evidence, too late; the realistic forward opportunities sit in secondary steel, outfitting consumables, and the maintenance and service tail after 2028 — and none of those are evidenced as open tenders here.

The substation jacket is the other steel-relevant package. At roughly 3,450 t and fabricated at Smulders HSM's River Tyne yard under a contract reported at more than £60 million, it is a meaningful UK-fabricated structural package — but it too is awarded and under construction, not an open opportunity.

Installation: the Wind Ace changes the logistics

Cadeler's delivery of the A-class jack-up Wind Ace on 17 July 2026 is the operational milestone that makes the 2027 offshore campaign concrete. The vessel, built over about two years at COSCO Shipping Offshore in Qidong, China, is Cadeler's eleventh ship and is purpose-built for XXL monopiles and next-generation turbines: more than 17,600 t payload, 5,600 m² deck, and capacity to carry up to six sets of 2XL monopile foundations per load. It will work alongside an O-class vessel on EA2 following mobilisation.

The supply chain around that campaign is filling in. Hampidjan Advant is supplying HMPE lifting slings for the Wind Ace, with the largest specified at 64 m long and a 4,000 t minimum breaking load — a figure that gives a sense of the lift envelope the XXL monopiles demand. Fugro, under contract to Cadeler, will carry out post-installation seabed surveys at all 64 monopile locations from early 2027, using an FCV 600 ROV deployed from an installation vessel.

Separately, GEOxyz is running a geophysical site survey over roughly 218 km² at the EA2 site with the vessel Geo Ocean IV, expected to complete around 30 October, weather permitting. This is site-characterisation and pre-construction survey work, not a structural package.

Timeline

DateMilestone
Sept 2024CfD awarded in AR6 (963.07 MW, £58.87/MWh 2012 prices)
Oct–Nov 2024Sif/Smulders foundation award; Cadeler T&I contracts signed
2025HSM Offshore Energy EPCIC award for the offshore substation
March 2026Topside and jacket construction begins
H2 2026Monopile and TP production scheduled to start
17 July 2026Cadeler takes delivery of Wind Ace
Early 2027Fugro post-installation surveys; offshore installation campaign begins
Q3 2027Jacket installation planned
Late 2028Commercial operation expected

What to watch

Three things will determine whether EA2 holds its late-2028 COD. First, Sif's Maasvlakte 2 ramp-up: Sif reported in its July 2026 interim results that East Anglia production was progressing to plan and the expanded factory had reached its planned ramp-up rate, but the first EA2 monopile has not been publicly dated or specified. Second, the interface between foundation fabrication in Rotterdam and the Wind Ace's installation sequence — a six-foundations-per-load capability only pays off if the fabrication line and the vessel schedule stay in step. Third, the substation programme, where a 5,100 t topside in the Netherlands and a 3,450 t jacket on Tyneside must converge on a Q3 2027 installation window.

For the steel industry, EA2 is best understood as a completed procurement with a visible tonnage consequence rather than an open market. The heavy plate is bought; the public record simply does not say by whom, in what grades or at what tonnage — and that opacity is itself worth noting as UK and European offshore wind scales toward the 2028–2030 build-out.