voestalpine has passed the point in its greentec steel programme where construction is still an open question. In October 2026 the group confirmed that assembly of the electric arc furnace at Donawitz was complete, and its H1 2026/27 interim report states that both furnaces remain on schedule and within budget, with commissioning planned for the first half of calendar year 2027. What remains is installation completion, cold and hot commissioning, and first heat — not the awarding of major plant or structural packages.
That distinction matters for anyone scanning the programme for commercial openings. The headline equipment contracts were signed in 2023 and 2024, the principal structural steelwork award followed in October 2024, and civil works at Linz are due to wind down in early 2027. The greentec steel story from here is a commissioning and market story, with one genuinely open frontier: the second Donawitz phase.
Where the programme actually stands
| Site | Operator | EAF supplier | Status (late 2026) |
|---|---|---|---|
| Linz | voestalpine Stahl GmbH (Steel Division) | Primetals Technologies — EAF Ultimate, 180 t heat | Installation/assembly; EAF building erected; civil works to Feb 2027; commissioning targeted H1 2027 |
| Donawitz (Leoben) | voestalpine Stahl Donawitz GmbH (Metal Engineering Division) | Danieli — DIGIMELTER | Furnace assembly completed October 2026; commissioning targeted H1 2027 |
| Donawitz Phase 2 | voestalpine Stahl Donawitz | Not disclosed | Decision taken Q1 FY2026/27, subject to funding approvals; ~€100m; full electrified production targeted 2030 |
Phase 1 carries an investment volume of around €1.5 billion for the two furnaces, described by voestalpine as Austria's largest climate protection programme. The Donawitz share is put at roughly €420 million in the site's current official material; the implied Linz remainder of about €1.0–1.1 billion is arithmetic, not a figure the company states as such. The stated target is a ~30% reduction in Scope 1+2 CO2 by 2029 against 2019, equivalent to around 4 Mt of CO2 per year and roughly 5% of Austria's national emissions.
Capital intensity is visible in the interim accounts. In April–September 2026 the Steel Division invested €307.8 million (+43% year on year) and the Metal Engineering Division €135.9 million (+27.8%), with greentec steel phase 1 named as the primary driver in both. Group capex for the half was €530.4 million.
The delivery model: no single EPC
One question that recurs around this project — who is the EPC contractor — has a straightforward answer: there isn't one. voestalpine runs the programme itself, through multi-project internal structures, and contracts the technology houses to coordinate their own installation and commissioning.
At Donawitz, Danieli & C. Officine Meccaniche was awarded the furnace in summer 2023 and acts as central partner coordinating installation of the core EAF elements and commissioning, alongside dust removal and heat recovery. voestalpine's October 2026 release notes more than 70 companies involved at Donawitz, around 90% of them Austrian, with roughly 500 workers on site.
At Linz, Primetals Technologies (Mitsubishi Heavy Industries group) was contracted in January 2024 for a complete 180-tonne EAF Ultimate, dedusting, waste-heat recovery feeding steam back into other plant units, alloy and additive handling, full Level 1 and 2 automation, STATCOM for grid stabilisation and LiquiRob robotic assistance. Primetals describes the furnace as designed for approximately 1.6 Mt of liquid steel annually; voestalpine's site material refers to more than 500 suppliers, over 90% Austrian, plus a 220 kV power-supply expansion, substations and a microtunnel.
A capacity note worth flagging: Danieli's 2023 announcement describes its order as two Digimelters configured initially for up to 107 t/h combined and up to ~1 Mt/yr, while voestalpine cites about 850,000 t/yr of reduced-CO2 steel at Donawitz. Equipment capability and planned output are simply different numbers.
Steel procurement: effectively closed for Phase 1
The structural steelwork for the Linz electric steelmaking complex was awarded in October 2024 to Haslinger Stahlbau GmbH. The package covers the EAF1 building, the Secondary Metallurgy 5 hall and a casting-hall extension, officially stated at around 13,500 tonnes of steel. Trade coverage (SOLID) cites approximately 15,500 tonnes; the company's own figure should be treated as authoritative, with the trade number possibly reflecting a broader scope.
Civil and foundation works at Linz were executed by PORR Bau GmbH — EAF hall and plant foundations, the LD3 extension, pipe-bridge foundations, substations and SekMet 5 infrastructure — under a project period running from June 2024 to February 2027. Combined with the erection of the roughly 100 m × 60 m × 65 m EAF building in a live-steelworks environment, this places the heavy steel phase of Phase 1 essentially behind the programme.
To state it plainly: for structural and mechanical steel suppliers, greentec steel Phase 1 is not an open opportunity. Any residual steel demand will be small, installation-related and internal to existing contracts. The forward-looking item is Donawitz Phase 2 — around €100 million covering additional power-supply capacity, a third secondary-metallurgy line and expanded scrap logistics — but that remains expressly subject to funding approvals and no procurement has been evidenced. Treat any Phase 2 supply angle as speculative until voestalpine announces it.
What to watch through 2027
- Linz commissioning sequence. Cold and hot commissioning of a 180-tonne furnace in a live works is the schedule-risk point, not fabrication. The first half of 2027 window is voestalpine's stated target; the precise date within it has not been published.
- Donawitz start-up. With assembly complete, the furnace moves to electrical, automation and process commissioning — the phase in which Danieli's coordinating role is most exposed.
- Feedstock economics. Both furnaces are designed for scrap, with Donawitz also using molten pig iron and HBI. Scrap logistics is already the subject of the Phase 2 expansion, which signals where voestalpine sees the binding constraint on full electrification.
- Market context. The programme is being commissioned into a soft European steel environment; voestalpine lowered its full-year EBITDA forecast alongside its H1 2026/27 results. The 2029 CO2 target stands regardless, but the commercial case for green premium products will be tested.
An economic impact study by the Industrial Science Institute, presented at the 2023 groundbreaking, modelled €767 million of value creation in Austria during construction and around 9,000 jobs secured — modelled estimates, not audited outcomes. Funding support comes through the Austrian climate ministry's environmental support programme; subsidy amounts are not publicly quantified in the material reviewed.
The practical reading for the supply chain: greentec steel has moved from a construction story to a technology and commissioning story. The participants are set, the steel is in place, and the next meaningful commercial signal will come from Donawitz Phase 2 funding decisions rather than from the 2027 start-up itself.