Oklo's Groves Isotope Test Reactor (Groves-1) cleared the US Department of Energy's final operations hold point in mid-November 2026, moving from a fuel-loaded critical assembly to an unrestricted research, testing and training platform in a span of roughly 13 months from groundbreaking. That timeline — not the reactor's tiny power output — is the story worth understanding.
What Groves-1 is, precisely
Groves-1 is a zero-power critical assembly, not a power reactor. DOE's NEPA categorical exclusion (CX-271014) sets its maximum power level at 100 watts, with the core reaching criticality under low heat generation. It sits at 2600 Mineral Springs Road in Lockhart, Caldwell County, Texas, inside the "Proto-Town" development — a site on private land rather than a DOE or national laboratory reservation.
The regulatory pathway matters. Groves-1 operates under DOE authorization under the Atomic Energy Act as a research and demonstration facility, not under an NRC operating licence. DOE's federal action was to authorize Oklo to possess nuclear fuel and operate the assembly. This is the same authorisation track DOE has used for the broader cohort of advanced reactor demonstrations under its Reactor Pilot Program (RPP).
| Item | Detail |
|---|---|
| Owner / developer / operator | Oklo Inc. (NYSE: OKLO) |
| Maximum power | 100 W (zero-power critical assembly) |
| Location | Proto-Town, Lockhart, Caldwell County, Texas |
| Regulatory basis | DOE authorisation (Atomic Energy Act), not NRC licence |
| Federal programme | DOE Reactor Pilot Program (selected Aug 2025, one of 11 projects) |
| Footprint / cost (state filing) | ~7,600 sq ft industrial facility; ~US$23 million estimated |
| General contractor | Century Construction (per subcontractor disclosure) |
| Electrical / I&C | Facility Solutions Group (FSG) |
The timeline is the headline
| Date | Milestone |
|---|---|
| Aug 2025 | Selected into DOE's Nuclear Reactor Pilot Program |
| 20 Oct 2025 | Construction start (Texas TDLR filing) |
| 23 Jul 2026 | DOE startup authorisation — fuel loading and criticality cleared |
| 5 Aug 2026 | First criticality, under a year after groundbreaking |
| 11–12 Nov 2026 | Final DOE operations hold point cleared; unrestricted operation |
- 2025-08-01Groves-1 was selected by the US Department of Energy in August 2025 as one of 11 advanced reactor projects for the Nuclear Reactor Pilot Program.
- 2026-08-01Groves-1 reached first criticality in August, less than a year after groundbreaking.
- 2026-11-12The US Department of Energy cleared the final operations hold point, allowing unrestricted operations and entry into research, testing and training.
Oklo frames the compressed schedule as evidence that a private developer can design, build and commission a critical assembly in about ten months on a greenfield private site. That claim is directionally supported by the Texas Department of Licensing and Regulation (TDLR) record, which also registers the project as "Inspection Complete" at the time of the filing. Note the TDLR registration was submitted in March 2026, after construction had already begun — a compliance timing footnote rather than a safety issue, but one that confirms the build moved fast enough to outrun its paperwork.
Groves-1 was the fifth DOE-authorised advanced reactor to reach criticality in the summer of 2026, alongside Antares Nuclear, Valar Atomics, Deployable Energy and Aalo Atomics. Read collectively, these are not isolated curiosities; they represent a deliberate DOE push to demonstrate that authorisation pathways can keep pace with private construction.
Why it matters commercially
The immediate output is negligible — 100 W does not light a streetlamp. The commercial value is threefold:
- Manufacturing credibility. Oklo states it manufactured or commercially procured all components, including fuel, and developed operating programmes in-house. For a company whose commercial model depends on serial production of small fast reactors (the Aurora line), proving it can assemble a working critical assembly on schedule is a reference point that matters to customers and investors.
- The isotope bridge. Groves-1 is intended as a testbed for isotope production experience, feeding into the planned Groves-2 Forge — a separate, more ambitious facility combining reactor irradiation with hot-cell processing, isotope separation, recovery, packaging and transport, initially targeting lutetium-177. Oklo announced Groves-2 Forge in October 2026 as part of DOE's Nuclear Energy Launch Pad selection. Groves-2 remains at concept stage; any supplier or procurement opportunity attached to it is speculative and not evidenced.
- Institutional learning. Oklo says Groves-1 will continue evaluating control-rod drive mechanism (CRDM) performance and reliability during routine operation. The CRDM supplier is not disclosed in any public source reviewed.
Procurement: what is closed and what is not
The facility is built and operating. Structural steel, the reactor assembly and the electrical/instrumentation scope have been delivered. Readers should treat Groves-1 as a completed procurement, not an open opportunity.
| Package | Status |
|---|---|
| General construction (facility) | Complete — Century Construction |
| Electrical, instrumentation, controls, testing, verification | Complete — FSG |
| Reactor components and fuel | Complete — Oklo in-house / commercially procured |
| CRDM evaluation programme | Ongoing operational activity; supplier undisclosed |
| Groves-2 Forge | Concept stage; no procurement evidenced |
Oklo has said more than 20 companies were contracted during construction, most Texas-based, but has not published a component-level supplier list. Any future steel or fabrication opportunity is therefore best framed around Groves-2 Forge and Oklo's separate Aurora deployments — neither of which has yet reported a steel package. For steel suppliers, Groves-1's relevance is indirect: it is a proof point in a broader industrial pattern where advanced nuclear developers compress schedules, and where demand for specialty and structural steel will eventually scale with commercial deployments, not test assemblies.
The facility was designed by Hillside Architecture (Austin) as architect of record per the TDLR filing; the owner of record is Mineral Springs Frontier LLC, and the tenant is listed as Thomas Eiden — reinforcing that this is a privately-owned site with Oklo as tenant-developer rather than landowner.
What remains uncertain
- The EPC/EPCI structure, if any, is not disclosed. Century Construction is identified as general contractor, but no design-build or full-scope EPC contract value is public.
- No reactor-vessel fabricator, fuel supplier or CRDM manufacturer has been publicly named.
- The advancement of Groves-2 Forge and the commercial Aurora fast reactor remain the developments to watch; the former was announced as a Launch Pad project in October 2026 and is still in concept phase.
Groves-1 is therefore best read as a proof-of-process asset: modest in physical scale, meaningful as evidence of how fast the US can now move from site mobilisation to criticality under a DOE pathway. Whether that speed translates into commercial steel and equipment demand depends on what comes next — Groves-2 Forge and Aurora, neither of which has yet crossed into procurement visibility.