POSCO has moved its hydrogen steelmaking ambitions from laboratory to construction site. In April 2026 the company began building a 300,000 tonne-per-year HyREX demonstration plant at its Pohang Works, on roughly 1.35 million m² of reclaimed land off Korea's southeast coast. Completion is targeted for 2028, followed by staged trial operation running to 2030 to lock in optimal operating conditions, with commercialization technology to follow.

The project sits inside a larger government-backed frame: Korea's K-GX signature programme, under which POSCO Group has proposed a "steel GX-based decarbonization industrial ecosystem" linking Pohang and Ulsan into a southeast-region cluster for clean hydrogen supply, hydrogen-reduction ironmaking and low-carbon steel demand — with an intended later expansion toward Gwangyang in the southwest.

This article looks at what the facility actually is, why POSCO chose a technology route that differs from most of its global peers, where the timeline has moved, and what remains commercially unresolved.


What HyREX actually does

HyREX is POSCO's proprietary hydrogen reduction ironmaking route. Its process chain has two distinctive stages:

  1. Multi-stage fluidized-bed reactors reduce fine iron ore with hydrogen to produce direct reduced iron (DRI).
  2. An electric smelting furnace (ESF) melts that DRI to produce molten iron.

The fluidized-bed choice is the technical heart of the story. Most commercial direct-reduction capacity worldwide uses shaft furnaces (MIDREX- or HYL-type), which require high-grade DR pellets — a feedstock POSCO notes accounts for only a few percent of global iron ore supply. Fluidized beds can consume ordinary medium- and low-grade iron ore fines directly. For a steelmaker that buys ore rather than mines it at scale, that is a raw-material security and cost argument as much as a decarbonization one.

The process also builds on POSCO's own industrial history. The company commercialized FINEX, a fluidized-bed ironmaking process, in 2007, and has operated it with reducing gas containing roughly 25% hydrogen. HyREX is in effect the hydrogen-maximized descendant of that platform — which matters for how quickly POSCO can plausibly scale it.

Precursor facilities (the de-risking path)

FacilityScaleTimingPurpose
Hydrogen fluidized-bed reduction furnace50 kg/batch2023, Pohang Technical Research InstituteValidate hydrogen fluidized-bed reduction
Electric smelting furnace (ESF) test unit1 tonne/hourApril 2024, Pohang Works (first tap achieved)Establish ESF elemental technology
HyREX demonstration plant300,000 t/yConstruction from April 2026; completion 2028Prove commercial viability by 2030

POSCO also established a dedicated Hydrogen Reduction Ironmaking Development Center at Pohang Works, consolidating the HyREX task force with R&D, engineering and construction personnel — a structural signal that this is being run as a build programme, not a research project.


Why fluidized beds are the interesting bet

The global green-steel conversation is often framed as a race to build hydrogen DRI shaft furnaces. POSCO is pursuing a genuinely different operating envelope:

  • Feedstock flexibility. Shaft furnaces are tied to scarce, premium DR-grade pellets. Fluidized beds open the door to fines. If DR-pellet supply tightens as dozens of hydrogen projects are built globally, this becomes a structural advantage rather than a technical footnote.
  • Prior operating experience. FINEX gives POSCO real fluidized-bed operating data at commercial scale — a shorter learning curve than a first-of-a-kind shaft furnace.
  • Cost exposure. The counter-argument is electricity. Hydrogen production and the ESF are both power-intensive, and Korean industrial electricity prices are a recurring concern in domestic coverage of the project's economics. Cost, not carbon chemistry, may be the harder variable to solve.

The site: reclaimed land, and a permitting milestone

The demonstration plant is being built at Pohang Works, on a reclaimed area of approximately 1.35 million m² (about 410,000 pyeong) on public waters north of Songjeong-dong, Nam-gu, Pohang.

Land permitting began in 2021. The decisive milestone came in March 2026, when the Ministry of Land, Infrastructure and Transport approved and gazetted the revision to the Pohang National Industrial Complex plan — clearing the way for construction to start the following month. That approval-to-construction sequence is unusually compressed, and reflects how much preparatory work had already been done.


The timeline has moved — and earlier targets have been reset

This is worth flagging for anyone tracking the project from older documents. POSCO's earlier public statements (2022–2023) targeted 2027 completion of a 300,000 t/y test facility. The current ESG disclosure states construction start April 2026, completion 2028, with trial operation continuing to 2030.

That is not simply a slip — it is part of a staged logic: build, then spend roughly two years tuning operating conditions before claiming a commercial-ready technology package.

The commercialization target — securing HyREX commercialization technology by 2030 — has remained stable across POSCO communications. Beyond that, the stated plan is progressive conversion of existing blast furnaces to HyREX as infrastructure, policy and market conditions allow.


Who is involved

ActorRole
POSCO Group / POSCO Holdings / POSCOOwner and developer
Primetals TechnologiesJoint engineering and design of the demonstration plant main facilities
POSCO InternationalDomestic offshore wind/solar, overseas energy portfolio
POSCO E&CEPC capability across energy and industrial plant
HyREX R&D Partnership~19 participating companies (global steelmakers, raw material suppliers and others) since 2023

Primetals Technologies is the notable technology partner. POSCO and Primetals signed a joint engineering cooperation agreement in July 2022, and Primetals — which co-designed POSCO's FINEX facilities — is co-designing the HyREX demonstration plant's main facilities. POSCO has explicitly linked that agreement to supporting the demonstration plant's EPC scope.

What is not yet visible: an awarded construction EPC contractor. As of the available evidence, no contractor has been publicly identified for the physical construction of the demonstration plant. That is a material open item — and, for the supply chain, a pending opportunity. Similarly, FEED, EPC award and major equipment procurement schedules have not been disclosed.


The K-GX frame: cluster economics and clean hydrogen

POSCO's K-GX proposal extends well beyond one plant. The southeast-region cluster concept connects Pohang and Ulsan industrial complexes around three linked elements:

  • clean hydrogen supply — including POSCO International's domestic offshore wind and solar generation;
  • hydrogen-reduction ironmaking capacity (HyREX); and
  • low-carbon steel demand, including a green premium market mechanism to monetize lower-carbon steel.

Reported cluster-level expectations include roughly KRW 6 trillion in economic effect, on the order of 11,000–14,000 jobs (figures vary by source), and about 560,000 tonnes per year of additional carbon reduction.

Two caveats matter here. First, these are cluster-level projections, not verified outcomes. Second — and more importantly for anyone modelling the project — the clean hydrogen supply source, volume and associated infrastructure plan have not been specified in the public material reviewed. A hydrogen-reduction plant without a settled hydrogen supply chain is a plant with a residual execution risk that sits outside POSCO's direct control.


Investment scale: read the numbers carefully

Reported capital figures for HyREX vary by source and scope — one Korean financial outlet cites KRW 1.6 trillion for the HyREX programme, while other coverage references roughly KRW 800 billion for the demonstration effort. The divergence almost certainly reflects different boundaries (demonstration plant alone vs. broader programme including hydrogen and conversion), and POSCO has not published a single canonical figure in the sources reviewed. Treat any specific number as scope-dependent rather than definitive.


What this means

For the steel industry, HyREX is the most consequential open question in Korean steelmaking: whether a fluidized-bed hydrogen route can be proven at 300,000 t/y and then replicated across blast-furnace capacity by the 2030s. If it works, POSCO gains a feedstock-agnostic decarbonization path that most shaft-furnace competitors cannot match.

For suppliers and contractors, the near-term signal is a large, permitted, funded construction project at Pohang with an EPC award still pending, and a hydrogen supply infrastructure requirement that is, as yet, undefined. Both are places where procurement activity should be expected — but neither has a published timeline.

For policymakers and the K-GX programme, Pohang is the test case for whether signature projects convert into industrial ecosystems. The cluster's clean hydrogen link is the piece most likely to determine whether the 2028 completion date translates into 2030 commercialization.


Open questions worth tracking

  • Who is awarded the construction EPC contract, and on what schedule?
  • What is the precise site layout and process scope of the demonstration plant?
  • Where does the clean hydrogen come from, at what volume and cost, and via what infrastructure?
  • What are the steel specifications and volumes required for the build and conversion works?
  • What is the concrete timeline and procurement scope for the planned Gwangyang-centred southwest expansion?

References

  1. 2026-09-14POSCO announced plans to complete a HyREX hydrogen-reduction steelmaking demonstration facility in Pohang in 2028 and pursue commercialization technology by 2030.
  2. 2026-10-07포스코그룹이 정부 K-GX 시그니처 프로젝트에 참여해 HyREX를 중심으로 한 철강산업 탈탄소 전환 및 산업 생태계 구축 계획을 발표했다.
Recorded development milestones for the HyREX demonstration project and its K-GX framing, as captured in project records.Credit: MetalMate · Original diagram (MetalMate)