Hornsea 3 has passed a quiet but significant threshold. Both offshore HVDC converter stations are on the seabed, monopile installation is in progress, and Ørsted has begun moving installation crews into position for the 197-turbine campaign. For supply-chain watchers, though, the more instructive story is upstream of the waterline — where a 2.9 GW order for XXL monopiles was split, partly re-tendered, and reassembled across three European fabricators.
Where the project actually stands
Hornsea 3 sits roughly 120 km off Norfolk and 160 km off Yorkshire in the Hornsea Zone. At 2.9 GW it is Ørsted's largest single project in development (after Hornsea 1 and 2) and uses 197 Siemens Gamesa SG 14-236 DD machines — down from an early design assumption of up to 231 turbines, a reduction that concentrated nameplate capacity into fewer,larger units.
Status is not uniform across the project's components, and the distinction matters commercially:
| Component | Supplier / Contractor | Current status |
|---|---|---|
| Offshore converter platforms (topsides) | Aibel (Map Ta Phut → Haugesund), Hitachi Energy HVDC Light | Both installed offshore |
| Offshore converter jackets (~3,500 t each) | Heerema Fabrication Group (Vlissingen), design by Enersea | Both installed (Link 1 ~54 m, Link 2 ~60 m) |
| Monopile foundations | Haizea Wind (Bilbao), EEW Special Pipe Constructions, formerly SeAH Wind | Under installation; first unit installed 2026 |
| Wind turbine generators | Siemens Gamesa | Turbine installation campaign mobilising |
| Onshore converter stations (Weybourne/Norwich Main) | Hitachi Energy; groundworks P.J. Hegarty | Under construction |
| Inter-array and export cabling | Not confirmed in public sources reviewed | — |
The converter-station chain is effectively closed. Heerema Marine Contractors lifted the jackets, drove eight skirt piles and set both topsides under a 2022 award from Aibel; the second unit went in during 2026. Steel fabrication for the platforms themselves is complete — the Link 1 topside loaded out of Thailand at roughly 9,560 tonnes, while Nordic Steel supplied about 130 tonnes of ventilation ducting per platform as a sub-component.
The monopile order was the real supply-chain test
Monopiles dominate Hornsea 3's steel demand. Ørsted's September 2022 awards split the scope between Haizea Bilbao and SeAH Wind, with units specified at 1,300–2,400 tonnes and 83–111 m — squarely in the XXL bracket that Europe's fabrication base was only then tooling up to produce.
That order did not survive intact. SeAH Wind, whose Teesside (Teesworks) facility was effectively launched on the back of this contract, saw its Hornsea 3 manufacturing-and-supply scope ended by mutual agreement; EEW Special Pipe Constructions subsequently appears in the fabrication mix, with units up to roughly 1,700 tonnes and 93 m. Haizea has remained in place, delivering from Spain — first monopiles arrived in the UK in early 2026.
On tonnage: reported unit weights (1,300–2,400 t) and an average of roughly 1,670 t per monopile imply a total monopile mass in the order of 330,000 tonnes. Cadeler's project disclosures cite approximately 400,000 tonnes of material transported for the project overall, which is a logistics figure, not a steel-only figure. Both are estimates derived from published unit data, not confirmed project totals; plate specifications and steel grades were not disclosed in the sources reviewed.
The practical implication for steel suppliers is that this is largely history. Haizea and EEW hold the remaining monopile scope; the fabrication awards were made in 2022 and the installation campaign is now the binding constraint. Any forward-looking opportunity sits with turbine towers and transition pieces and with whatever cable and onshore steelwork packages remain unconfirmed — but the evidence for those is thin, and readers should treat them as unverified rather than as open tenders.
Why the HVDC choice matters beyond this project
Hornsea 3 is the first phase in the Hornsea cluster to use HVDC rather than HVAC transmission — a consequence of distance and capacity. Hitachi Energy's two HVDC Light converter systems serve four converter stations (two offshore, two onshore), with the landfall at Weybourne feeding Norwich Main.
The unmanned platform design, developed jointly by Aibel and Hitachi Energy and built around lean steel jackets, is the template for how remote, high-capacity North Sea wind will be connected. That has two downstream effects worth tracking: first, it creates a repeatable fabrication product — a converter platform jacket-plus-topside — that Heerema Fabrication Group and Aibel can bid for elsewhere; second, it shifts the balance of project value away from turbine count and toward electrical infrastructure, where steel content per megawatt is much higher.
The topology also explains why the converter stations were installed before the turbines: grid infrastructure has to be ready to accept first power, so the HVDC chain cannot be the critical path late in construction.
What to watch
The near-term focus is the turbine installation campaign. DEME's jack-up Norse Energi has mobilised at Able Seaton Port, following the arrival of the first Siemens Gamesa component sets in mid-2026. Monopile installation is running in parallel. The genuinely open questions — cable supply and installation contractors, commissioning dates, and the commercial structure of the remaining balance-of-plant — are not resolved in the public record and should not be assumed.
For the steel industry, Hornsea 3 is less a live order book than a case study: a 2.9 GW project that consumed several hundred thousand tonnes of foundation steel, demonstrated European XXL monopile capacity under strain, and proved that a single contract award in this market can make or break a fabrication facility.

