The moment a 1,700-tonne piece of steel stood up
At Heerema Fabrication Group's Vlissingen yard in the Dutch province of Zeeland, two cranes have done something that looks deceptively simple and is anything but: they lifted a 1,700-tonne steel assembly from horizontal to vertical. In offshore fabrication parlance this is a "roll-up," and it is the moment a jacket substructure stops being a collection of shop-fabricated subassemblies and starts becoming a structure.
The element is the first completed structural section of the jacket foundation for TenneT's IJmuiden Ver Beta 2 GW offshore converter platform, a project that will anchor one of the largest HVDC grid connections in the North Sea. The milestone was reported by Offshore Wind in late August 2026, roughly a year after the first steel was cut at the same yard in September 2025.
This article explains what is being built, why the jacket matters far beyond its own tonnage, and where the project sits in the wider Dutch and European 2 GW programme.
What exactly is IJmuiden Ver Beta?
It is important to separate three things that share the name IJmuiden Ver Beta:
| Layer | Who owns it | What it is |
|---|---|---|
| The wind farm | Zeevonk II (Vattenfall–Copenhagen Infrastructure Partners JV) | ~2 GW offshore wind, plus a planned floating solar array and an onshore electrolyser concept |
| The grid connection | TenneT | A 2 GW, 525 kV HVDC offshore converter platform and its export cable to the Maasvlakte |
| The platform structure | GE Vernova–Seatrium consortium (EPC), Heerema Fabrication Group (jacket fabrication) | A steel jacket substructure plus a ~30,000-tonne topside housing the converter |
The wind farm was awarded in June 2024 under the Dutch government's IJmuiden Ver tender. TenneT, as the Dutch and much of the German transmission system operator, is responsible for getting the power ashore. The platform — not the turbines — is the subject of the fabrication milestone above.
IJmuiden Ver Beta is one of four Dutch 2 GW connections TenneT is building under a standardised design philosophy: IJmuiden Ver Alpha, IJmuiden Ver Beta, IJmuiden Ver Gamma and Nederwiek 2. The Beta platform is widely described by the engineering community as the "blueprint" for the others, which is why its progress carries disproportionate weight.
The structure: bigger than it sounds
Numbers around this jacket have circulated in slightly different forms. Here is what the available sources support:
- Jacket weight: in excess of 10,000 tonnes (Heerema describes it as "more than 10,000 tonnes"; TenneT states approximately 10,000 tonnes).
- Dimensions: Heerema gives roughly 90 m high and 43 m wide; TenneT describes it as about 100 m long, 50 m wide and 50 m high. The discrepancy reflects whether transport (horizontal, on a barge) or installed (vertical) orientation is being quoted, and which extremities are counted. Treat ~10,000 t and a footprint in the 40–55 m range as the reliable figures.
- Topside weight: nearly 30,000 tonnes, per TenneT — a useful reminder that the jacket is a supporting actor in tonnage terms even though it is the piece currently in fabrication.
The jacket is an eight-leg frame. TenneT's published design documentation notes it is engineered to be installable by more than one method, including catamaran and float-over approaches — a deliberate choice that gives the installer flexibility and reduces schedule risk. That design detail matters commercially: it means the jacket and topside installation strategy can adapt to vessel availability rather than being locked to a single heavy-lift asset.
Why this milestone is more than a photo opportunity
A roll-up is a genuine engineering gate. Until an element is verticalised, the fabricator is still accumulating subassemblies. After roll-up, the geometry is set, the tolerances have held through a load case that stresses the assembly differently from anything it experienced in the shop, and the path to load-out becomes measurable.
For a jacket of this size, the sequencing matters because Vlissingen's load-out capacity is finite. Heerema's Vlissingen yard has a 200,000 m² site, a 720 m quay and load-out capability of up to 20,000 tonnes. That is comfortably sufficient for a 10,000-tonne jacket, but it also means the yard's calendar is the binding constraint across the three jackets it is building — Beta, Gamma and Nederwiek 2 — not any single structure.
That triple-booked order book is the real story. Heerema is not building one jacket; it is running a small production line of near-identical 2 GW jackets, which is exactly what TenneT's standardisation strategy was designed to enable.
- 2025-09-01Jacket construction began in September 2025 with the first steel cut.
- 2025-09-01The first steel was cut for the IJmuiden Ver Beta jacket.
- 2025-09-01Fabrication of the jacket began at Heerema Fabrication Group's Vlissingen yard.
- 2026-08-31Heerema Fabrication Group completed the first structural element and performed the first roll-up, lifting the 1,700-tonne steel element from horizontal to vertical using two cranes.
The procurement chain behind the steel
The contractual layering is worth spelling out, because it explains why a Dutch yard is building a structure for a consortium whose topside is being assembled in Singapore.
- TenneT awarded a framework agreement and call-offs for 2 GW HVDC systems. GE Vernova and Seatrium (formerly Sembcorp Marine) were confirmed for the Dutch projects in March 2023, with the three Dutch 2 GW projects collectively valued at roughly €6 billion. Seatrium's own disclosure puts each Dutch project at approximately €2 billion.
- GE Vernova–Seatrium hold the EPC scope: engineering, procurement, construction, transportation, installation and commissioning of the converter platforms.
- Heerema Fabrication Group was contracted by that consortium to fabricate the jackets. It is a subcontract position, which is why the first steel cut for the topside in Singapore (September 2024) and the first steel cut for the jacket in Vlissingen (September 2025) are separate milestones with separate press cycles.
For steel-industry readers, the notable gaps are the ones that are usually most interesting: the jacket's plate and tubular grades, the tonnage split between rolled plate and seamless or welded tubulars, and the identity of the mills supplying the steel. None of these have been disclosed in the available public material. What can be said with confidence is that a 10,000-tonne offshore jacket in the North Sea is a substantial structural-steel order — dominated by heavy plate for the legs and nodes — and that Dutch and wider European fabricators are positioning for exactly this kind of standardised, repeatable offshore-wind work.
The timeline that really governs the project
The fabrication milestones are visible because fabricators publicise them. The dates that actually drive the project sit in the tender schedule and the grid-connection agreement:
| Date | Milestone |
|---|---|
| March 2023 | GE Vernova–Seatrium confirmed for Dutch 2 GW HVDC projects |
| 11 June 2024 | Zeevonk II (Vattenfall–CIP) wins IJmuiden Ver Beta tender |
| 11 September 2024 | First steel cut for the topside at Seatrium's Tuas Boulevard yard, Singapore |
| September 2025 | First steel cut for the jacket at Heerema's Vlissingen yard |
| Late August 2026 | First jacket element completed and rolled up (1,700 tonnes) |
| 31 May 2029 | TenneT platform must be ready for wind-farm cable pull-in |
| 31 October 2029 | Wind farm ready to supply at least 70% of guaranteed HVDC capacity |
| 30 November 2029 | Full power |
| 31 January 2030 | HVDC grid connection delivery |
Those 2029–2030 dates come from the published IJmuiden Ver tender milestone schedule. They are the numbers that matter. The gap between the roll-up in August 2026 and the cable pull-in deadline in May 2029 is not generous when it contains: completion of the jacket, load-out, transport, installation, the topside's own Singapore completion, its transport and installation, offshore commissioning, and the export cable works.
The wind farm's operational deadline is also referenced elsewhere as 2029, which is consistent with the tender schedule above. TenneT has separately stated that the Beta design-input and connection-agreement dates were unaffected by tender changes — a signal that the transmission side was being deliberately insulated from developer-side uncertainty.
Where the risk sits
Three areas deserve attention from anyone tracking this project:
Concurrency at Vlissingen. Heerema is fabricating three jackets for the same programme. Gamma's construction started in September 2026 with a sail-out scheduled for summer 2028. Beta's jacket must progress in parallel. Yard space, skilled welders and crane availability — not steel supply — are the probable constraints.
Topside–jacket interface timing. A jacket that is ready before its topside, or a topside waiting on a jacket, both cost money in vessel standby. The float-over and catamaran installation options in the design give TenneT optionality, but optionality is only valuable if the two halves are ready within the same window.
Onshore-side coupling. The Beta connection lands at the Maasvlakte. Parliamentary material has noted that delays to the Delta Rhine Corridor affected the Zeevonk project and that permit amendments were under discussion. Offtake-side and hydrogen-side ambition around IJmuiden Ver Beta — the electrolyser concept, the floating solar element — add political and permitting surface area that a grid-connection schedule cannot control.
What to watch next
For industry professionals, the next genuinely informative events are not the ones with press releases. They are:
- The Beta jacket's load-out, which will confirm the final as-built weight and dimensions, resolving the current inconsistency between sources.
- Any disclosure of the steel supply chain — mill, grades, and whether plate is European or imported.
- The installation contract and vessel assignment, which will indicate whether TenneT is executing the catamaran or float-over route.
- Whether the Gamma jacket's September 2026 start has any knock-on effect on Beta's schedule, given the shared yard.
IJmuiden Ver Beta's jacket is, in isolation, a large steel frame. In context, it is the test case for whether TenneT's decision to standardise four 2 GW platforms — and to let a Dutch yard build the substructures in series — can hold to a schedule that leaves little slack. The roll-up in Vlissingen is the first hard evidence that the series production is real.