TenneT's LanWin2 is no longer a contract story. Within roughly 14 months, the 2 GW HVDC connection in the German North Sea has acquired a complete industrial supply chain and started converting it into steel and cable. The critical recent milestone is the award to Eiffage — through its Belgian subsidiary Smulders — of a subcontract from Dragados Offshore to fabricate the jacket foundation for the LanWin beta converter platform. That closes the last obvious structural-steel gap in the offshore package: the substructure now has a named fabricator, the topside has been in block production since September 2025, and the export cable is being extruded in Norway.
For steel suppliers, the commercial window is narrower than the project's 2030 commissioning date suggests. Almost every large-tonnage package described below has been competitively awarded. Any remaining tonnage sits inside the fabricators' own procurement — plate and tubulars bought by Smulders, Cimolai and Eversendai from European mills and distributors — rather than in open TenneT or Dragados tenders.
What LanWin2 actually is
LanWin2 is one of TenneT's standardised 2 GW offshore grid connections: a 525 kV HVDC XLPE system that collects AC power from North Sea wind farms at an offshore converter platform (LanWin beta), converts it to DC offshore, and transmits it via roughly 250 km of onshore and offshore export cable to the Heide region of Schleswig-Holstein. This is the German sector of the North Sea, and it nearly doubles the capacity of TenneT's earlier 900 MW-class connections.
The project is delivered under two distinct contracting tracks that are now both in execution:
| Package | Supplier | Award basis | Status |
|---|---|---|---|
| LanWin beta converter platform (topside) | Siemens Energy / Dragados Offshore consortium | Multi-year framework with TenneT (April 2023) covering BalWin3, LanWin2, LanWin4 | Fabrication started — first steel cut September 2025 |
| Export cable system (~250 km, 525 kV HVDC XLPE) | Nexans | €1 billion project under May 2023 TenneT frame agreement, awarded 15 Jan 2025 | Industrial cable production started October 2026 at Halden, Norway |
| Jacket foundation for LanWin beta | Eiffage (Smulders) via Dragados Offshore subcontract | Announced 16 November 2026 | Fabrication in Belgium and Poland; assembly and load-out in the Netherlands; construction start early 2027, load-out target 2030 |
| Jacket structural design | KCI (Sif Group subsidiary) | Contract from Dragados Offshore (announced September 2025) for LanWin2 and BalWin3 | Engineering scope, including German BSH compliance |
The platform: distributed fabrication, Spanish integration
The offshore converter platform is being built in a deliberately dispersed way. Block fabrication began in September 2025 at Cimolai in Italy and Eversendai in the UAE (Ras Al Khaimah). Eversendai's own announcement places its first-steel-cut ceremony on 18 September 2025, while trade press dated the milestone 30 September — a minor discrepancy worth noting, but not material to the schedule. Completed blocks are shipped to Dragados Offshore's Algeciras yard in Spain for integration, outfitting and testing.
The scale is substantial but should be treated carefully. Public references put each platform topside at roughly 24,000 tonnes and each jacket at around 10,000 tonnes; other summaries describe an all-in 34,000 tonnes per station. These figures come from consortium and trade material rather than verified fabrication drawings, so they are best used as order-of-magnitude guidance, not procurement specification.
What the jacket award tells us
The Smulders/Eiffage contract is the most informative recent development because it reveals how the substructure market is being organised. The jacket is not single-sourced from one yard:
- Fabrication of steelwork split between Belgium and Poland — leveraging Smulders' existing yard network rather than building new capacity;
- Final assembly and load-out in the Netherlands, positioning the completed jacket for North Sea installation;
- Construction start early 2027, with load-out targeted for 2030.
Three things follow. First, the jacket programme is only just beginning: while the topside has been cutting steel since 2025, the jacket's steel demand falls largely in 2027–2029. Second, that demand will be procured by Smulders and its Polish and Belgian operations — the steel-plate and heavy-tubular supply chain that feeds those yards — not through a fresh TenneT or Dragados tender. Third, the early-2027 start means that if there is any residual opportunity for plate and tubular suppliers to engage, it is at the fabricator tier in the coming quarters.
Note also the engineering link: KCI, a Sif Group subsidiary, holds the design contract for the LanWin2 and BalWin3 jackets, including compliance with Germany's Federal Maritime and Hydrographic Agency (BSH) requirements. Design at KCI, fabrication at Smulders, integration at Dragados — a genuinely multi-country chain.
The cable track is arguably the bigger technical milestone
The Nexans award is worth more (€1 billion) and carries more novel content than is often recognised. In October 2026, Nexans began industrial-scale production of 525 kV HVDC XLPE subsea cable at Halden, Norway — describing it as the first industrial-scale output of this technology following qualification. High-voltage XLPE was historically the weak point in the DC transition; demonstrating reproducible 525 kV extrusion at scale matters well beyond this one project, because TenneT's wider 2 GW programme depends on it.
The cable's own steel content — armouring wire and related reinforcement — is real but sits deep inside Nexans' supply chain and is not a comparable procurement story to the platform structures.
Where the steel actually sits
LANWin2's steel footprint is concentrated in three places, and their commercial status differs sharply:
| Steel element | Approx. scale (unverified) | Procurement status |
|---|---|---|
| Platform topside blocks | ~24,000 t | Awarded — Cimolai (IT), Eversendai (UAE); fabricated to Dragados design |
| Jacket foundation | ~10,000 t | Awarded — Smulders (BE/PL); construction 2027, load-out 2030 |
| Cable armouring | Not disclosed | Embedded in Nexans supply chain |
There is no evidence of an open structural-steel package still awaiting award at project level. The platform consortium and the jacket subcontract are fixed. The realistic reading is that the headline fabrication contracts are settled and the remaining steel activity is second-tier procurement by the fabricators — plate and tubular orders placed against Smulders' 2027–2030 programme being the main live area. The detailed grades, plate thicknesses and tonnages for the jacket are not public, and neither are mill nominations — so any supplier interest has to go through the fabricators rather than the developer.
Timeline and what to watch
- April 2023 — Siemens Energy/Dragados framework with TenneT for BalWin3, LanWin2, LanWin4.
- May 2023 — Nexans framework agreement with TenneT.
- 15 January 2025 — Nexans awarded LanWin2 (~€1 billion), with commissioning then expected 2030.
- September 2025 — first steel cut for the converter platform in Italy and the UAE; KCI jacket design contracts announced.
- October 2026 — Nexans begins industrial-scale 525 kV XLPE cable production at Halden.
- 16 November 2026 — Smulders wins the LanWin beta jacket subcontract.
The milestones that matter next are all fabrication and integration events rather than awards: arrival of first topside blocks at Algeciras, the start of jacket steelwork in early 2027, load-out around 2030, and ultimately installation and commissioning. Fugro's completion of survey work for TenneT's German 2 GW projects points to site preparation proceeding in parallel.
The bigger context
LanWin2 is one of several 2 GW platforms in a TenneT programme that is reshaping the European offshore converter supply chain into a few deeply integrated consortia — Siemens Energy/Dragados for topsides, Nexans for cables, and Smulders and Cimolai/Eversendai for structures. That concentration brings schedule discipline but also single-points of dependency across a multi-country fabrication chain spanning Italy, the UAE, Belgium, Poland, the Netherlands, Spain and Norway.
For steel professionals, the takeaway is that LanWin2 has largely passed the point where primary structural procurement is open. Its remaining significance is as a reference project: it demonstrates the tonnage scale, fabrication geography and subcontracting model that the next wave of 2 GW North Sea platforms — BalWin3, LanWin4 and successors — will replicate, and it shows where plate and tubular demand will land as the 2027–2030 jacket cycle begins.
- 2025-01-15Nexans secured the approximately EUR 1 billion LanWin2 contract under a 2023 TenneT framework agreement, covering EPC and installation of about 250 km of 525 kV HVDC onshore and offshore export cable
- 2025-01-15Nexans secured the approximately €1 billion contract for LanWin2 under a framework agreement signed with TenneT in 2023, covering EPCI of around 250 km of 525 kV HVDC onshore and offshore export cable
- 2025-09-01First steel for the offshore converter platform was cut in September 2025 at Dragados Offshore facilities in Italy and the United Arab Emirates.
- 2025-09-30First steel was cut for the offshore converter platform, which is being delivered by the Siemens Energy and Dragados Offshore consortium.
- 2025-09-30First steel was cut for the LanWin2 offshore converter platform in September 2025.
- 2026-10-16Nexans began industrial-scale production of 525 kV HVDC XLPE subsea cables for LanWin2 at its Halden, Norway facility.
- 2026-10-16Nexans began industrial-scale production of 525 kV HVDC XLPE subsea cables for LanWin2 at its Halden, Norway facility.