Nordion Energi's liquefied biogas (LBG) plant at Skarvik 4 in the Port of Gothenburg has passed a visible construction milestone: the 500 m³ cryogenic storage tank — close to 140 tonnes, with capacity for roughly 200 tonnes of LBG — was lifted into place and announced on 13 November 2026. Groundworks and foundation slabs are done, the turnkey liquefaction supplier is named, and a specialist subcontractor is installing insulated pipework and loading skids. The commercial operation date, however, has moved from "autumn 2026" to "Q2 2027."
For an industry audience the project matters for two reasons. It is Sweden's first LBG plant connected directly to the gas grid (as Nordion bills it), drawing biomethane from existing infrastructure rather than a single digestion plant — a template for converting grid biomethane into a marine and heavy-road fuel. And it is at the stage where the large fabricated items are in the ground and the remaining work is predominantly piping, skids and commissioning.
What is being built, and by whom
The contracting entity is Swedegas AB, Nordion's gas-grid subsidiary. The core lot — a turnkey liquefaction plant with purification, plus the 500 m³ tank — was tendered under an EU utilities procedure (ref. 24/118, "LBG Liquefaction from grid") published in April 2024, with an estimated value of SEK 130 million excluding VAT and an option to double both liquefaction and storage capacity.
| Element | Capacity / detail | Status |
|---|---|---|
| Liquefaction output | 250 GWh/yr ≈ 50 t/day LBG | Under construction |
| Storage tank | 500 m³, ~140 t, ~200 t LBG capacity | Installed (Nov 2026) |
| Grid connection | New pipeline bridge from the west Sweden gas grid | Constructed as part of 2026 works |
| Turnkey supplier | Wärtsilä (awarded June 2025) | Under construction |
| Piping / loading skids | Apex IS (Sertion subsidiary): LBG lines, vacuum-insulated piping, loading skids, supplier coordination | Under construction, completion targeted autumn 2026 |
| Offtake | St1 Biokraft holds part of capacity | Signed |
The SEK 130 million figure is the tender's estimate for the turnkey lot, not a confirmed contract price, and is unlikely to represent Nordion's full investment once civil works, the pipeline bridge, land arrangements and financing are counted. Treat it as a benchmark, not a settled project value.
Timeline: a documented slip
The schedule has moved steadily since the December 2024 investment decision:
- Dec 2024: investment decision; completion targeted autumn 2026.
- June 2025: Wärtsilä contract; plant delivery September 2026, operation "before the end of 2026."
- May 2026: construction start announced; completion "2027."
- Nov 2026: tank installed; inauguration now targeted for Q2 2027.
That is roughly a six- to seven-month slip against the original plan. The port's own November language is looser still ("during 2027"), and no exact commissioning date has been published. Readers planning around the plant's output should treat Q2 2027 as a target rather than a fixed date.
Where the steel sits
The 500 m³ tank is the project's most conspicuous steel item, but its fabrication is effectively closed: the unit is delivered and set. Nordion has not named the tank manufacturer, and no public source in the record confirms which fabricator supplied it. The same applies to the tank's steel specification — cryogenic LBG service typically requires a low-temperature inner vessel material and an outer carbon-steel shell, but the specific grades used here are not disclosed.
What remains underway is the fabricated pipework and equipment scope handled by Apex IS — vacuum-insulated LBG lines and loading skids — plus the Wärtsilä liquefaction train and its ancillary steel-intensive equipment. These are within awarded scopes, not open market packages, so there is no evidence of remaining primary steel procurement opportunity for outside suppliers. Any maintenance or expansion work is speculative at this stage.
Why the Q2 2027 date is commercially significant
The output is aimed squarely at marine bunkering and heavy road transport, and the port frames it as enabling large-scale LBG bunkering from 2027 — roughly 50 vessels' worth annually, or the yearly consumption of about 500 trucks. Nordion cites a Swedish LBG market expected to exceed 10 TWh by 2030, against biogas already supplying 39.3% of gas on the west Sweden network in Q1 2025 and a stated 100% biogas target by 2030.
For shipowners and hauliers weighing fuel conversions, the plant's start date is the binding constraint on local LBG availability; a further slip would push the region's bunkering proposition into late 2027. For the supply chain, the remaining milestones — mechanical completion, pipeline and skid installation, commissioning and inauguration — are the ones to watch.