Revolution Wind has reached the milestone that matters most commercially: full commissioning. The 704 MW project south of Rhode Island is delivering power to Rhode Island and Connecticut, and all 67 monopile foundations and 65 Siemens Gamesa SG 11.0-200 DD turbines are in place. For the steel supply chain that built it, the build is over.

The notable story now is not construction but the contest over its permit. Within weeks of the project entering full operation, the Department of Justice and Department of the Interior asked the US District Court for the District of Columbia to remand the project's Construction and Operations Plan (COP) approval so Interior can reassess compliance with the Outer Continental Shelf Lands Act (OCSLA). That is a live regulatory risk hanging over an operating asset — and a template other US offshore wind projects may face.

What the project actually is

ParameterDetail
Capacity704 MW
Location~15 miles south of Rhode Island; ~32 miles southeast of Connecticut
Turbines65 × Siemens Gamesa SG 11.0-200 DD
Foundations67 steel monopiles (65 WTG + 2 offshore substation)
Offshore substations2, supplied by Kiewit Offshore Services
Offtake400 MW Rhode Island; 304 MW Connecticut (20-year PPAs)
OwnersØrsted 50%, Skyborn Renewables (GIP) 50%
StatusFully commissioned; delivering power

The offtake is contracted to Rhode Island Energy (PPL), Connecticut Light & Power (Eversource) and United Illuminating (Avangrid) — the project is expected to power more than 350,000 homes and businesses.

Steel: a large, closed procurement

Revolution Wind was a substantial steel project, and the relevant fact for suppliers is that essentially all of it has been awarded, fabricated and installed. The table below separates what is finished from what is not.

Steel packageStatusNotes
Monopile foundations (67)InstalledBladt Industries (Denmark) fabricator; Boskalis transport & installation
Transition pieces / secondary steelInstalledBoskalis Bokalift 1 installed secondary steel
Offshore substations (2)InstalledKiewit Offshore Services design-and-build
Wind turbine towersInstalledSiemens Gamesa scope
Inter-array / export cable armourInstalledCable contractor not confirmed in public sources reviewed

A few points worth flagging for anyone using this as a benchmark:

  • Tonnage is not officially published. The largest installed turbine foundation weighed about 2,105 tonnes, per Boskalis reporting. A rough arithmetic estimate for all 67 monopiles lands in the range of 140,000–150,000 tonnes before transition pieces, secondary steel and towers — but this is an analyst estimate, not a disclosed figure, and should be treated as indicative only.
  • The foundation supplier was Bladt, not EEW. Ørsted's Q4 2023 transcript identifies Bladt as the foundation supplier for Revolution Wind and Sunrise Wind, and cited ramp-up and transportation challenges affecting delivery schedules. Bladt's 2022 annual report lists "Revolution Wind 1" with a 2021 contract award. EEW's published monopile references include Vineyard Wind but not Revolution Wind.
  • There is no single turnkey EPC. Ørsted acted as developer and construction manager across a set of separate contracts: Bladt (monopiles), Boskalis (foundation and substation T&I, plus scour protection), Kiewit (substations), Siemens Gamesa (turbines, installation, service). This disaggregated model is typical of US offshore wind and matters when modelling contract structures.
  • Forward steel demand from this project is not evidenced. Ongoing requirements are operational service and maintenance; nothing in the public record indicates further fabrication packages are open.

The ownership shift that changed the risk profile

Eversource, originally a 50% partner alongside Ørsted, exited. In February 2024 it agreed to sell its 50% interests in Revolution Wind and South Fork Wind to Global Infrastructure Partners for expected proceeds of roughly $1.1 billion. The deal closed on 30 September 2024 at adjusted gross proceeds of $745 million — materially below the headline expectation — and Eversource booked an aggregate after-tax loss of about $524 million on its 2024 offshore wind divestitures. Skyborn Renewables, a GIP portfolio company, now manages that stake.

The practical read: an infrastructure investor with a long horizon now holds half the asset, while Ørsted — which took large US impairments in this period — retains the other half and the construction legacy. That structure shapes how the two owners will approach the remand fight.

Construction was interrupted twice, and completed anyway

The build did not proceed smoothly. In August 2025, with the project around 80% complete, the US government issued a stop-work order; a federal court allowed work to resume the following month. A second stop-work order citing national security concerns followed in December 2025 and was blocked by the court in January 2026. Despite this, first power to the New England grid came in March 2026, the final turbine was installed in September 2026, and full commissioning was reached in October 2026.

That sequence is instructive: judicial intervention allowed a nearly complete project to finish, but at real cost in schedule and likely in contractor standing time. For vessel operators and installation contractors, the lesson is that late-stage political interruption is now a credible scheduling risk on US offshore wind, not a tail event.

Where this leaves the remand

The DOJ/DOI motion of 9 October 2026 asks the court to send the COP approval back to Interior for reassessment of OCSLA compliance. What that ultimately means — a procedural correction, modified conditions, or something more disruptive — is genuinely uncertain, and no outcome should be assumed. What is clear is the unusual posture: the government is seeking to revisit the permit of a fully built, operating, contracted generator.

Industry professionals watching US offshore wind should treat Revolution Wind as the leading indicator. If remand leads only to adjusted conditions, the precedent is manageable. If it becomes a route to unwind approvals already relied upon by financed, operating projects, the implications run well beyond this one wind farm — into the cost of capital, contract bankability and the willingness of steel and fabrication suppliers to commit capacity to US offshore wind at all.

For now, the steel is in the water and the power is flowing. The question is whether the paperwork behind it will hold.

Map of the Revolution Wind lease area off the Rhode Island and Connecticut coast with grid connection points
Revolution Wind lease area and associated onshore infrastructure, per BOEM.Credit: BOEM · Public domain · source