Industrial projects, independently researched.

Steel-intensive projects investigated from primary sources by MetalMate’s AI research analyst. Each article is AI-generated and should be independently verified.

113 published projects6 industries8 regions

20 of 113 projects

Reset all filters
EuropeConstruction / fabrication
AI-generated image
EuropeConstruction / fabrication

Marcegaglia's €1.2bn Fos-sur-Mer EAF: Mistral financing is in place — but the FID still isn't

Marcegaglia has locked in €800m of SACE/Bpifrance-backed sustainability-linked debt and a €450m Danieli equipment contract for its Mistral electric-furnace steel complex at Fos-sur-Mer, but final investment decision, permits and the civil-works/construction-steel packages are all still outstanding ahead of a target 2029 start-up.

Industry & mining · Updated 2026-11-07
AI-generated image
EuropeConstruction / fabrication

East Anglia Two moves into the delivery phase: foundations, the Wind Ace and what the steel procurement record actually shows

ScottishPower Renewables' 960 MW East Anglia Two has moved into construction, with Sif and Smulders building 64 monopiles and transition pieces, HSM the offshore substation, and Cadeler's new Wind Ace due to install from 2027; the monopile plate supply chain remains largely undisclosed.

Offshore renewables · Updated 2026-11-04
AI-generated image
EuropeConstruction / fabrication

Keel Laid at Nantong: Wison's Sakarya Phase 3 FPU Enters Hull Assembly, With Steel Work Only Half Done

Wison New Energies has laid the keel for TPAO's 282 m Sakarya Phase 3 FPU in Nantong, moving a 25,000 t topsides and ultra-deepwater hull into assembly — but the schedule stated to Türkiye's state oil company and the timeline reported by trade press differ by roughly a year, and steel supply details remain undisclosed.

Energy · Updated 2026-11-03
AI-generated image
EuropeConstruction / fabrication

East Anglia Three: Foundations In, Turbines Turning — Inside the 1.4 GW Build and Its Spanish Steel Backbone

All 95 monopiles and transition pieces at East Anglia Three are installed and the 240 km inner-array cable campaign is complete, with 95 Siemens Gamesa 14 MW turbines going up ahead of a targeted end-2026 commissioning. A look at the multi-contract delivery model, the now-closed foundation supply chain and what remains.

Offshore renewables · Updated 2026-11-02