Industrial projects, independently researched.

Steel-intensive projects investigated from primary sources by MetalMate’s AI research analyst. Each article is AI-generated and should be independently verified.

113 published projects6 industries8 regions

54 of 113 projects

Reset all filters
Europe
EuropeContract award

LanWin2 Moves Into Steel: TenneT's 2 GW North Sea Link Enters Fabrication as Jacket Award Completes the Supplier Map

With Nexans extruding 525 kV cable at Halden, Siemens Energy/Dragados cutting first steel in Italy and the UAE, and Eiffage Smulders now contracted for the LanWin beta jacket, TenneT's 2 GW LanWin2 connection has moved decisively from award to fabrication — and the remaining steel demand is concentrated in the platform topside and jacket programmes already placed.

Offshore renewables · Updated 2026-11-17
AI-generated image
EuropeConstruction / fabrication

Marcegaglia's €1.2bn Fos-sur-Mer EAF: Mistral financing is in place — but the FID still isn't

Marcegaglia has locked in €800m of SACE/Bpifrance-backed sustainability-linked debt and a €450m Danieli equipment contract for its Mistral electric-furnace steel complex at Fos-sur-Mer, but final investment decision, permits and the civil-works/construction-steel packages are all still outstanding ahead of a target 2029 start-up.

Industry & mining · Updated 2026-11-07
AI-generated image
EuropeConstruction / fabrication

East Anglia Two moves into the delivery phase: foundations, the Wind Ace and what the steel procurement record actually shows

ScottishPower Renewables' 960 MW East Anglia Two has moved into construction, with Sif and Smulders building 64 monopiles and transition pieces, HSM the offshore substation, and Cadeler's new Wind Ace due to install from 2027; the monopile plate supply chain remains largely undisclosed.

Offshore renewables · Updated 2026-11-04
AI-generated image
EuropeConstruction / fabrication

Keel Laid at Nantong: Wison's Sakarya Phase 3 FPU Enters Hull Assembly, With Steel Work Only Half Done

Wison New Energies has laid the keel for TPAO's 282 m Sakarya Phase 3 FPU in Nantong, moving a 25,000 t topsides and ultra-deepwater hull into assembly — but the schedule stated to Türkiye's state oil company and the timeline reported by trade press differ by roughly a year, and steel supply details remain undisclosed.

Energy · Updated 2026-11-03
AI-generated image
North America · EuropeAnnounced

A Framework, Not a Contract: What the Swiss Steel–Canada Nickel 1 Mt/y Low-Carbon Billet Plan Actually Commits To

Swiss Steel and Canada Nickel have signed only a framework of intent for up to ~1 Mt/y of low-carbon stainless and specialty billets and blooms from 2030. The real story is the two-year schedule gap between Crawford's 2029 start and Swiss Steel's industrial strategy — and who carries that risk.

Industry & mining · Updated 2026-11-02
AI-generated image
EuropeConstruction / fabrication

East Anglia Three: Foundations In, Turbines Turning — Inside the 1.4 GW Build and Its Spanish Steel Backbone

All 95 monopiles and transition pieces at East Anglia Three are installed and the 240 km inner-array cable campaign is complete, with 95 Siemens Gamesa 14 MW turbines going up ahead of a targeted end-2026 commissioning. A look at the multi-contract delivery model, the now-closed foundation supply chain and what remains.

Offshore renewables · Updated 2026-11-02
AI-generated image
EuropeAnnounced

RESOLVE: Aker Solutions Wins EU Innovation Fund Selection for Automated HVDC Topside Steel Fabrication Line

Aker Solutions' RESOLVE project has been selected under the EU Innovation Fund's IF25 manufacturing call to build an automated laser-hybrid welding line for offshore wind HVDC topside steel structures, claiming ~10 months of schedule savings — but the grant is unsigned and no site, capex, tonnage or steel specification has been disclosed.

Offshore renewables · Updated 2026-11-02